Harristown SES facility faces proposed $57,535 infrastructure-charge waiver

Toowoomba’s Planning and Development Committee has recommended waiving the full charge for the approved facility at 489 - 491 South Street; the supplied record does not show a final Council decision.

Published 13 November 2026From the 10 November 2026 meeting1 min read
Illustration, not a depiction of the actual site or project.

Reporting from public council minutes. How this article was prepared

A proposed Queensland State Emergency Service facility in Harristown could avoid a $57,535.20 infrastructure charge after Toowoomba Regional Council’s Planning and Development Committee recommended a full waiver.

The charge applies to the approved emergency-services development at 489 - 491 South Street under permit MCUC/2026/3278. The council report says the amount was issued under Charges Resolution No. 7 and is subject to indexation.

Under the committee’s recommendation, Council would also delegate implementation to the chief executive officer, including entering an Infrastructure Agreement. A Council determination is required, and the supplied minutes do not record a final Council vote.

The waiver would sit outside the council’s 2.44 Development Incentive - Not-for-Profit Community Uses Policy. That policy provides emergency services with a discount on development application fees, but not infrastructure charges. It allows a 75 per cent infrastructure-charge discount for public benevolent institutions, health promotion charities and community-based organisations, capped at $250,000 and unavailable where discounts have been applied to application fees.

The report presented three options: decline the request, approve a 75 per cent concession, or waive all infrastructure charges. The committee recommended the third option. If Council approves it, the report says up to $57,535.20, plus indexation, in charge revenue may not be realised.

The Queensland SES asked for the charge to be waived or substantially reduced. Its submission said the facility would provide a base for volunteers carrying out emergency response, storm and flood operations, land searches, road crash rescue support and disaster recovery, as well as training and equipment storage.

Those are claims made in the SES submission and recorded in the council report. Officers noted they had not independently verified the SES claim that the infrastructure charge had affected the project’s viability. The supplied minutes also do not establish when the facility will open or confirm that the development will proceed.

What deserves a closer look

The supplied record does not establish whether Council will adopt the committee's recommended waiver or what terms would govern its implementation.

The proposed concession would be outside the current policy framework and could reduce charge revenue by up to $57,535.20 plus indexation.

Questions for follow-up reporting

When would Council determine the committee's recommendation?

What terms would apply under any Infrastructure Agreement?

What is the expected opening timetable for the Harristown facility?

Would indexation alter the charge before any agreement is completed if a concession is approved?

What happens next

A Council determination would be needed to approve the proposed infrastructure-charge concession.

If Council approves a concession and the proposed delegation, the chief executive officer would take the necessary implementation steps, including entering an Infrastructure Agreement.

Check the record

These passages were matched to the source text. Read them in context in the original minutes.

The committee recommended that Council waive all infrastructure charges and delegate implementation to the chief executive officer, including entering an Infrastructure Agreement.
COMMITTEE RECOMMENDATION That Council: 1. Approve a waiver of all infrastructure charges; and 2. Delegate to the Chief Executive Officer to take actions as necessary to give effect to the decision of Council, including the entering into of an Infrastructure Agreement to apply any infrastructure charges concession.

Item 5, Committee Recommendation

Open original minutes ↗
An emergency-services development permit, MCUC/2026/3278, was issued for 489–491 South Street, Harristown. The proposed SES facility's infrastructure charge was $57,535.20 under Charges Resolution No. 7, subject to indexation.
BACKGROUND A development permit for a Material Change of Use - Emergency Services (MCUC/2026/3278) was issued on 17 July 2026, over 489-491 South Street, Harristown, described as Lot 14 on GTP104958. The development is for a proposed Queensland State Emergency Services (SES) facility, with a copy of the approved plans of development available in Attachment 3. Council issued an Infrastructure Charges Notice for the development on 3 September 2026, under Charges Resolution No. 7. A copy of the Infrastructure Charges Notice is contained in Attachment 4. This notice levies an infrastructure charge of $57,535.20 for the proposed use, subject to indexation.

Item 5, Background

Open original minutes ↗
The policy provides emergency services with a development-application fee discount but no infrastructure-charge discount. It provides a 75 per cent infrastructure-charge discount, capped at $250,000, for public benevolent institutions, health promotion charities and community-based organisations, but not where discounts have been applied to application fees.
Under Section 4.2 of the Policy, a 100% discount of the development application fee up to $20,000 is applicable for Emergency Services. No infrastructure charges discounts are supported under the policy. A 75% discount up to $250,000 is applicable for infrastructure charges for Public Benevolent Institutions (PBIs), Health Promotion Charities (HPCs) and community-based organisations, but not for Emergency Services, and not where discounts have been applied to application fees.

Item 5, Background

Open original minutes ↗
The report provided three options: decline the request, approve a 75 per cent concession, or waive all infrastructure charges.
RECOMMENDATION That Council considers the request for an infrastructure charge concession for the proposed Emergency Services (SES facility) development MCUC/2026/3278 and resolves to: 1. Decline the request as ineligible for incentives; or 2. Approve an infrastructure charge concession of 75% consistent with the discounts offered to Public Benevolent Institutions (PBIs), Health Promotion Charities (HPCs) and community based organisations under 2.44 – Development Incentive – Not-for-Profit Community Uses Policy; or 3. Approve a waiver of all infrastructure charges; and 4. Delegate to the Chief Executive Officer to take actions as necessary to give effect to the decision of Council, including the entering into of an Infrastructure Agreement to apply any infrastructure charges concessions.

Item 5, Recommendation

Open original minutes ↗
The request required a Council determination because it sought assistance outside the adopted Development Incentive – Not-for-Profit Community Uses Policy.
REASONS FOR RECOMMENDATION The request seeks assistance outside Council's adopted 2.44 - Development Incentive - Not-for-Profit Community Uses Policy (Attachment 2) and therefore requires determination by Council.

Item 5, Reasons for Recommendation

Open original minutes ↗
Officers had not independently verified the applicant's claim that infrastructure charges had affected project viability and that the development might not proceed without Council assistance.
Page 242 of 271 Toowoomba Regional CouncilPlanning and Development Committee 10 November 2026 •Project Delivery Risk - The applicant has advised that infrastructure charges have affected project viability and that the proposed development may not proceed without Council assistance. Officers have not independently verified this claim; however, should the project not proceed, the anticipated public benefits associated with the development may not be realised. LEGAL ISSUES The current Policy does not provide infrastructure charges discounts for Emergency Services.

Item 5, Project Delivery Risk

Open original minutes ↗
If Council approves an incentive, appropriate legal documentation, including an Infrastructure Agreement, would be required.
Should Council determine to approve an incentive, appropriate legal documentation, including the drafting of an Infrastructure Agreement, would be required through Council's standard process.

Item 5, Legal Issues

Open original minutes ↗
If Council approves the request, infrastructure-charge revenue of up to $57,535.20 plus indexation may not be realised.
DELEGATION This matter requires determination by Council as it sits outside of the current policy framework and delegations to Council Officers. FINANCIAL/RESOURCE IMPLICATIONS Should Council determine to approve the request, infrastructure charge revenue of up to $57,535.20 plus indexation may not be realised.

Item 5, Financial/Resource Implications

Open original minutes ↗

Source record

Reporting from the supplied record of the Toowoomba Regional Council Planning and Development Committee meeting on 10 November 2026. The supplied extract is incomplete, and its confirmation status is not established.

Key facts from the minutes

  • The Planning and Development Committee recommended waiving all infrastructure charges for the SES facility at 489 - 491 South Street, Harristown.
  • The infrastructure charge was $57,535.20, subject to indexation, under Charges Resolution No. 7.
  • The committee recommended that Council delegate implementation to the chief executive officer, including an Infrastructure Agreement.
  • Emergency services are not eligible for infrastructure-charge discounts under Council’s current not-for-profit community uses policy.
  • The supplied minutes do not show a final Council decision or establish a facility completion date.

Why it matters

  • A full waiver could forgo up to $57,535.20 plus indexation in infrastructure-charge revenue for an SES facility at Harristown, while the proposed concession remains subject to a Council determination and would require an Infrastructure Agreement if approved.