Works & infrastructure · Randwick City Council
Randwick residents generally face the bill for underground powerlines
Council says it has no program to contribute to resident-initiated works, while its own undergrounding funds are tied to projects such as The Spot and Maroubra Junction streetscape upgrades.

Reporting from public council minutes. How this article was prepared
Randwick residents who ask for overhead powerlines to be buried will generally have to fund the work themselves, with Council saying it has no adopted program to contribute to resident-initiated projects.
In its response recorded in the unconfirmed minutes of the 17 November meeting, Randwick City Council said current funding for undergrounding was limited to specific streetscape and town-centre projects. It also said advice from Ausgrid indicated electricity distributors cannot co-fund or cost-share undergrounding with councils or other third-party proponents.
As a result, requesting landowners would generally be responsible for resident-initiated works, Council said. It added that recent enquiries had not identified a NSW Government grant program specifically established for undergrounding existing overhead power infrastructure at residents’ request.
The response covers Victory Street, Melrose Parade, Lowe Street, Cliffbrook Parade and the eastern end of Clovelly Road. Council said those properties are within the Foreshore Scenic Protection Area. The question’s preamble says Clovelly residents had petitioned for undergrounding near Clovelly Beach, with a concept plan costed at about $1.5 million. Council said it had not held discussions with Ausgrid about undergrounding in that precinct.
Council’s current funding for undergrounding is limited to specific streetscape and town-centre projects. The adopted four-year Delivery Program allocates $3.576 million to The Spot Streetscape Upgrade, including undergrounding existing overhead powerlines, with another $4.45 million identified between 2027/28 and 2029/30. The 2026-27 Operational Plan also includes $3,544,010 for the Maroubra Junction Streetscape Upgrade, which includes undergrounding powerlines.
Those allocations are project-specific and do not form part of a city-wide undergrounding program. Council said it has no established criteria or assessment framework for prioritising the precincts identified in Development Control Plan Part B14. It said undergrounding priorities have focused on town-centre masterplans and remain subject to funding and annual budget decisions.
The response also says three applications determined since the new DCP commenced on 27 July 2026 met the relevant threshold. All three had been lodged before that date, so the new provisions did not apply under the DCP’s savings provisions. Council said the new undergrounding requirements would apply at determination to relevant applications lodged from 27 July.
The minutes provide Council’s position and its account of advice from Ausgrid. They do not give a street-by-street cost estimate for resident-initiated works in the named streets or establish a timetable for a broader Council program.
What deserves a closer look
The supplied material for QN15/26 is a question with notice and an officer response, not a resolution approving undergrounding works or a new funding program.
Council's record distinguishes funding for named streetscape projects from a general undergrounding program. It does not establish that resident-initiated works in the named streets will receive funding through those projects.
The response states that there is no established prioritisation framework and supplies no ranked delivery timetable for the DCP's listed precincts; it does not establish that no timetable exists elsewhere.
Questions for follow-up reporting
How would the cost of resident-initiated undergrounding in the named streets or around Clovelly Beach be apportioned among individual landowners?
Will Council establish criteria or a timetable for assessing the DCP's listed undergrounding precincts?
Will Council or Ausgrid assess the feasibility and cost of the Clovelly Beach proposal?
Check the record
These passages were matched to the source text. Read them in context in the original minutes.
Council said it has no adopted budget or funding program enabling contributions to resident-initiated undergrounding, and its current adopted funding is limited to specific streetscape and town-centre improvement projects.
Council does not currently have an adopted budget or funding program that would enable financial contributions towards resident-initiated undergrounding of power lines. As outlined in the response to Question 3, Council's current adopted funding for the undergrounding of power infrastructure is limited to specific streetscapes and town centre improvement projects.
QN15/26, Director City Planning response, question 5
Open original minutes ↗Council said resident-initiated undergrounding projects are generally required to be funded by the requesting landowners.
Consequently, resident-initiated undergrounding projects are generally required to be funded by the requesting landowners which is consistent with previous examples in the Randwick LGA.
QN15/26, Director City Planning response, question 5
Open original minutes ↗Council said advice received from Ausgrid indicated that the National Electricity Rules do not permit electricity distributors to co-fund or cost-share undergrounding works with Council or other third-party proponents.
Advice received from Ausgrid indicates that the National Electricity Rules do not permit electricity distributors to co-fund or cost-share undergrounding works with Council or other third-party proponents.
QN15/26, Director City Planning response, question 5
Open original minutes ↗Council said recent enquiries had not identified current NSW Government grant programs specifically established to fund resident-initiated undergrounding of existing overhead power infrastructure.
Recent enquiries have not identified any current NSW Government grant programs specifically established to fund resident-initiated undergrounding of existing overhead power infrastructure.
QN15/26, Director City Planning response, question 5
Open original minutes ↗Council said the properties identified in the question—Victory Street, Melrose Parade, Lowe Street, Cliffbrook Parade and the eastern end of Clovelly Road—are within the Foreshore Scenic Protection Area.
4. Are Victory Street, Melrose Parade, Lowe Street, Cliffbrook Parade and the eastern end of Clovelly Road within the Foreshore Scenic Protection Area or an E1 Local Centre? These properties are located within the Foreshore Scenic Protection Area.
QN15/26, Director City Planning response, question 4
Open original minutes ↗Council said it had not held discussions with Ausgrid about undergrounding powerlines in the Clovelly Beach precinct.
6. Has Council discussed undergrounding around Clovelly Beach with Ausgrid? If so, has Ausgrid given any advice on cost or feasibility? Council has not held discussions with Ausgrid regarding the undergrounding of power lines in the Clovelly Beach precinct.
QN15/26, Director City Planning response, question 6
Open original minutes ↗Council reported $3.576 million allocated to The Spot Streetscape Upgrade under its adopted four-year Delivery Program, a further $4.45 million identified for that project between 2027/28 and 2029/30, and $3,544,010 allocated to Maroubra Junction Streetscape Upgrade in the 2026-27 Operational Plan. Both projects include undergrounding, and The Spot funding is project-specific rather than part of a broader city-wide undergrounding program.
Under Council's adopted four-year Delivery Program, $3.576 million has been allocated toward The Spot Streetscape Upgrade project. This project includes the undergrounding of existing overhead power lines in conjunction with broader public domain and streetscape improvement works. A further $4.45 million is identified between 2027/28 and 2029/30 for MINUTES OF ORDINARY COUNCIL MEETING 17 NOVEMBER 2026 This is page 19 of the Minutes of the Ordinary Council meeting held on 17 November 2026 delivery of The Spot Streetscape Upgrade. It should be noted that this funding is project- specific and does not form part of a broader city-wide powerline undergrounding program. Furthermore, Council has allocated $3,544,010 in the 2026-27 Operational Plan for Maroubra Junction Streetscape Upgrade which includes undergrounding powerlines.
QN15/26, Director City Planning response, question 3
Open original minutes ↗Council said it has no established criteria or assessment framework for prioritising the precincts identified in DCP Part B14 for undergrounding. Prioritisation has focused on town-centre masterplans and is subject to funding availability and annual operational-plan and budget consideration.
2. What criteria and process will Council use to assess E1 Local Centres and foreshore areas for its own undergrounding program? There are currently no established criteria or assessment framework for prioritising the precincts identified in Development Control Plan (DCP) Part B14: Communications and Power Lines for power line undergrounding. Power undergrounding projects prioritisation has been focused on Town Centre Masterplans and are subject to funding availability and Council consideration through the operational plan and budget process each year.
QN15/26, Director City Planning response, question 2
Open original minutes ↗Source record
Randwick City Council, unconfirmed Ordinary Council meeting minutes, 17 November 2026, item QN15/26, including the question’s preamble and the response from the Director City Planning.
Key facts from the minutes
- Council said it has no adopted budget or funding program for contributions to resident-initiated undergrounding.
- Council said resident-initiated works are generally required to be funded by requesting landowners, following advice it received from Ausgrid about restrictions on distributor co-funding.
- The Spot Streetscape Upgrade has $3.576 million allocated, plus a further $4.45 million identified between 2027/28 and 2029/30; Maroubra Junction Streetscape Upgrade has $3,544,010 allocated in 2026-27, with both projects including undergrounding.
- Council said there is no established criteria or assessment framework for prioritising the DCP’s undergrounding precincts; the response provides no ranked delivery timetable.
- The five named streets and road sections are within the Foreshore Scenic Protection Area, according to Council’s response.
Why it matters
- Residents considering undergrounding in the Foreshore Scenic Protection Area, around Clovelly Beach or elsewhere should not assume Council will share the cost. On the minutes’ record, Council funding is tied to separately funded streetscape and town-centre projects, while the response provides no ranked delivery timetable for wider precinct prioritisation.