Rates & spending · Randwick City Council

Randwick residents generally face the bill for underground powerline requests

Council has no adopted funding program for resident-initiated works, while millions allocated to The Spot and Maroubra Junction are tied to streetscape projects.

Published 19 November 2026From the 17 November 2026 meeting1 min read
Illustration, not a depiction of the actual site or project.

Reporting from public council minutes. How this article was prepared

Residents seeking to put overhead powerlines underground in Randwick City will generally have to fund the work themselves, with Council saying it has no adopted budget to contribute to resident-initiated projects.

A response recorded in Randwick City Council’s unconfirmed minutes says requesting landowners are generally required to pay for resident-initiated undergrounding. It also records Ausgrid advice that electricity distributors cannot co-fund or cost-share the work with councils or other third-party proponents under the National Electricity Rules.

The response concerns three pathways in Council’s Development Control Plan Part B14: a Council undergrounding program, development-funded works and resident-initiated projects. Council said recent enquiries had not identified a NSW Government grant program specifically established to fund resident-initiated undergrounding of existing overhead infrastructure.

Council does have funding for undergrounding where it forms part of particular streetscape projects. The adopted four-year Delivery Program allocates $3.576 million to The Spot Streetscape Upgrade, including undergrounding existing overhead lines, with a further $4.45 million identified between 2027/28 and 2029/30. The 2026-27 Operational Plan also includes $3,544,010 for the Maroubra Junction Streetscape Upgrade, which includes undergrounding powerlines.

Those allocations are project-specific and do not form part of a broader city-wide undergrounding program, according to the recorded response. Further opportunities are generally considered when undergrounding can be coordinated with major streetscape, town-centre renewal or public-domain projects, or delivered through developer-funded works under Council’s planning controls.

Part B14 lists E1 local centres and the Foreshore Scenic Protection Area as priority areas, but Council said there was no established criteria or assessment framework for ranking those precincts. Undergrounding priorities have instead focused on town-centre masterplans and remain subject to annual operational-plan and budget decisions.

The minutes also record that Council has not discussed undergrounding around Clovelly Beach with Ausgrid. The background to the question says Clovelly residents petitioned for the work and that a concept plan was costed at about $1.5 million. No Council contribution or delivery timetable is recorded for that proposal.

What deserves a closer look

The record distinguishes between undergrounding funded as part of named streetscape projects and resident-initiated work, for which Council says no contribution program exists.

Being listed as a priority area under Part B14 does not, on this record, provide a ranked delivery timetable.

The funding figures cover streetscape projects that include undergrounding; the record does not identify those entire amounts as undergrounding-only budgets.

Questions for follow-up reporting

What assessment process would apply if a resident-initiated request overlapped with a future streetscape or town-centre project?

What delivery timetable, if any, is proposed for the Clovelly Beach undergrounding request?

When, if at all, will Council establish criteria for ranking the Part B14 precincts?

Check the record

These passages were matched to the source text. Read them in context in the original minutes.

Council has no adopted budget or funding program for contributions to resident-initiated undergrounding, and requesting landowners generally fund those projects.
Council does not currently have an adopted budget or funding program that would enable financial contributions towards resident-initiated undergrounding of power lines. As outlined in the response to Question 3, Council's current adopted funding for the undergrounding of power infrastructure is limited to specific streetscapes and town centre improvement projects. Advice received from Ausgrid indicates that the National Electricity Rules do not permit electricity distributors to co-fund or cost-share undergrounding works with Council or other third-party proponents. Consequently, resident-initiated undergrounding projects are generally required to be funded by the requesting landowners which is consistent with previous examples in the Randwick LGA.

QN15/26, Director City Planning response to Question 5

Open original minutes ↗
The recorded Ausgrid advice says the National Electricity Rules do not permit electricity distributors to co-fund or cost-share undergrounding with Council or other third-party proponents.
Advice received from Ausgrid indicates that the National Electricity Rules do not permit electricity distributors to co-fund or cost-share undergrounding works with Council or other third-party proponents.

QN15/26, Director City Planning response to Question 5

Open original minutes ↗
The adopted four-year Delivery Program allocates $3.576 million to The Spot Streetscape Upgrade, which includes undergrounding, with a further $4.45 million identified for delivery between 2027/28 and 2029/30. The response says this funding is project-specific rather than part of a broader city-wide undergrounding program, and records $3,544,010 allocated in the 2026-27 Operational Plan to the Maroubra Junction Streetscape Upgrade, which also includes undergrounding.
Under Council's adopted four-year Delivery Program, $3.576 million has been allocated toward The Spot Streetscape Upgrade project. This project includes the undergrounding of existing overhead power lines in conjunction with broader public domain and streetscape improvement works. A further $4.45 million is identified between 2027/28 and 2029/30 for MINUTES OF ORDINARY COUNCIL MEETING 17 NOVEMBER 2026 This is page 19 of the Minutes of the Ordinary Council meeting held on 17 November 2026 delivery of The Spot Streetscape Upgrade. It should be noted that this funding is project- specific and does not form part of a broader city-wide powerline undergrounding program. Furthermore, Council has allocated $3,544,010 in the 2026-27 Operational Plan for Maroubra Junction Streetscape Upgrade which includes undergrounding powerlines.

QN15/26, Director City Planning response to Question 3

Open original minutes ↗
There are no established criteria or assessment framework for prioritising the Part B14 precincts for undergrounding; undergrounding prioritisation has focused on town-centre masterplans, subject to funding availability and annual Council consideration through the operational-plan and budget process.
2. What criteria and process will Council use to assess E1 Local Centres and foreshore areas for its own undergrounding program? There are currently no established criteria or assessment framework for prioritising the precincts identified in Development Control Plan (DCP) Part B14: Communications and Power Lines for power line undergrounding. Power undergrounding projects prioritisation has been focused on Town Centre Masterplans and are subject to funding availability and Council consideration through the operational plan and budget process each year.

QN15/26, Director City Planning response to Question 2

Open original minutes ↗
Council has not held discussions with Ausgrid about undergrounding powerlines in the Clovelly Beach precinct.
6. Has Council discussed undergrounding around Clovelly Beach with Ausgrid? If so, has Ausgrid given any advice on cost or feasibility? Council has not held discussions with Ausgrid regarding the undergrounding of power lines in the Clovelly Beach precinct.

QN15/26, Director City Planning response to Question 6

Open original minutes ↗
Clovelly residents have petitioned for undergrounding around Clovelly Beach, with a concept plan costed at about $1.5 million.
There are "subject to Council assessment". Under the resident-initiated pathway, residents must fund the full cost, and foreshore areas are a priority. Clovelly residents have petitioned for undergrounding around Clovelly Beach, with a concept plan costed at about $1.5 million.

QN15/26, preamble

Open original minutes ↗
Recent enquiries have not identified any current NSW Government grant programs specifically established to fund resident-initiated undergrounding of existing overhead power infrastructure.
Recent enquiries have not identified any current NSW Government grant programs specifically established to fund resident-initiated undergrounding of existing overhead power infrastructure.

QN15/26, Director City Planning response to Question 5

Open original minutes ↗
The question preamble describes three Part B14 pathways—Council, development-funded and resident-initiated undergrounding—and lists E1 Local Centres and the Foreshore Scenic Protection Area as Council-program priority precincts subject to Council assessment.
6. Has Council discussed undergrounding around Clovelly Beach with Ausgrid? If so, has Ausgrid given any advice on cost or feasibility? Preamble: Council's final Development Control Plan (DCP) Part B14: Communications and Powerlines, sets out three pathways for undergrounding power lines. These are a Council undergrounding program, development-funded undergrounding, and resident- initiated undergrounding. MINUTES OF ORDINARY COUNCIL MEETING 17 NOVEMBER 2026 This is page 18 of the Minutes of the Ordinary Council meeting held on 17 November 2026 The Council program lists priority precincts including E1 Local Centres and the Foreshore Scenic Protection Area. There are "subject to Council assessment". Under the resident-initiated pathway, residents must fund the full cost, and foreshore areas are a priority. Clovelly residents have petitioned for undergrounding around Clovelly Beach, with a concept plan costed at about $1.5 million.

QN15/26, Question 6 and preamble

Open original minutes ↗

Source record

Reporting from the unconfirmed public minutes of Randwick City Council’s Ordinary Council meeting held on 17 November 2026.

Key facts from the minutes

  • Council said it has no adopted budget or funding program to contribute to resident-initiated undergrounding.
  • The minutes record Ausgrid advice that distributors cannot co-fund or cost-share undergrounding with councils or other third-party proponents.
  • The Spot Streetscape Upgrade has $3.576 million allocated, with a further $4.45 million identified between 2027/28 and 2029/30; Council says this funding is project-specific.
  • The 2026-27 Operational Plan includes $3,544,010 for the Maroubra Junction Streetscape Upgrade, which includes undergrounding powerlines.
  • Council said there is no established framework for prioritising the Part B14 precincts and has not discussed Clovelly Beach undergrounding with Ausgrid.

Why it matters

  • Residents considering undergrounding works need to distinguish Council’s project-specific streetscape funding from the resident pathway, where requesting landowners generally fund the work themselves.