Rates & spending · Randwick City Council
$1.16m allocated to Burnie Street park, with early 2027 start anticipated
Randwick Council says construction is anticipated to start in early 2027, while three other projects in the Clovelly Road streetscape plan remain unfunded.

Reporting from public council minutes. How this article was prepared
Randwick Council has allocated $1,163,589 to the Burnie Street Pocket Park, with construction anticipated to begin in early 2027.
The project’s detailed design is near completion and the funding is included in the council’s adopted four-year Delivery Program, according to a response recorded in the minutes of the 17 November council meeting, treated here as unconfirmed.
The seven-project Clovelly Road Precinct Streetscape Master Plan has uneven progress. Gilderthorpe Avenue and Market Street is under design and has $700,000 in grant funding. Council said it is expected to be constructed after Burnie Street, but the minutes do not give it a start date.
Frenchman’s Road streetscape improvements are also under design and are partially funded, with $140,000 allocated in the adopted four-year Delivery Program. Carrington Road Pocket Park is complete and grant funded.
The Fern Street upgrade, Arden Street upgrade and Clovelly Beach public-domain improvements are listed as unfunded. Council said the remaining projects are not ranked as stand-alone capital works in the adopted Operational Plan, and their delivery will depend on council priorities, available funding, successful grant applications and future budget consideration.
The response also records $2.456 million spent since 2021-22 on projects associated with the Clovelly Road precinct and town-centre improvements. About $2.26 million came from NSW Government and other external grants, including Transport for NSW funding. The recorded expenditure covers several projects.
Council officers said they would create a designated website page with updates for each adopted master plan when available. Progress on funded projects will continue through existing reporting and budgeting processes. No timing is recorded for the three unfunded projects.
What deserves a closer look
The source records anticipated construction timing and funding allocations, not a guaranteed construction date.
The project pipeline combines one completed project, funded or partly funded projects, and three projects without identified funding.
The four expenditure entries sum to $2,456,202, matching the recorded total.
Questions for follow-up reporting
What construction timetable will apply to Gilderthorpe Avenue and Market Street after Burnie Street?
What additional funding is required for the Frenchman's Road streetscape improvements?
When, if at all, will Council nominate delivery dates for the three unfunded projects?
What happens next
Council officers said they would create a designated website page with updates when available for each adopted master plan.
The response says progress on funded projects will continue through Council's existing reporting and budgeting processes.
Check the record
These passages were matched to the source text. Read them in context in the original minutes.
Burnie Street Pocket Park is funded under the adopted four-year Delivery Program, with detailed design near complete and construction anticipated to commence in early 2027.
Delivery will be subject to Council priorities, available funding, successful grant applications and future budget consideration. Burnie Street Pocket Park is funded under the adopted four-year Delivery Program. Detailed design is near complete, with construction anticipated to commence in early 2027. 5. All of Council's Masterplans are currently available on Council's public website. Council Officers will create a designated page with updates when available on the website for each adopted Masterplan.
QN14/26 response, delivery and construction timing
Open original minutes ↗Gilderthorpe Avenue and Market Street and Frenchman's Road streetscape improvements have design underway; Carrington Road Pocket Park is completed.
The status of each of the seven priority projects within the Clovelly Road streetscape masterplan is outlined in the table below. Project Status Gilderthorpe Avenue and Market Street upgrade Design underway Frenchman's Road streetscape improvements Design underway Carrington Road Pocket Park: Completed Fern Street upgrade Not started Arden Street upgrade Not started Burnie Street Pocket Park Detailed design near complete.
QN14/26 response, project status table
Open original minutes ↗Burnie Street has $1,163,589 allocated in the adopted four-year Delivery Program; Gilderthorpe Avenue and Market Street has $700,000 in grant funding; Frenchman's Road has $140,000 allocated and is partially funded; Fern Street, Arden Street and Clovelly Beach public-domain improvements are unfunded. Carrington Road Pocket Park is completed and grant funded.
3. The funding status of remaining projects is: Project Funding status Gilderthorpe Avenue and Market Street upgrade Grant funded - $700,000 MINUTES OF ORDINARY COUNCIL MEETING 17 NOVEMBER 2026 This is page 17 of the Minutes of the Ordinary Council meeting held on 17 November 2026 Frenchman's Road streetscape improvements Partially funded - $140,000 - allocated in the adopted 4-year delivery program Carrington Road Pocket Park Completed - Grant funded. Fern Street upgrade Unfunded Arden Street upgrade Unfunded Burnie Street Pocket Park Funded - $1,163,589 allocated in the adopted 4-year delivery program Clovelly Beach public domain improvements Unfunded 4.
QN14/26 response, funding status table
Open original minutes ↗Gilderthorpe Avenue and Market Street is expected to be constructed next after Burnie Street. The remaining projects are not currently ranked as stand-alone capital works projects in the adopted Operational Plan, and delivery is subject to priorities, available funding, successful grant applications and future budget consideration.
Gilderthorpe Avenue and Market Street upgrade is expected to be constructed next after Burnie Street Pocket Park. The remaining projects are not currently ranked as stand-alone capital works projects within the adopted Operational Plan. Delivery will be subject to Council priorities, available funding, successful grant applications and future budget consideration. Burnie Street Pocket Park is funded under the adopted four-year Delivery Program.
QN14/26 response, delivery sequencing and conditions
Open original minutes ↗The response records $2,456,202 spent on associated Clovelly Road precinct and town-centre improvements since 2021-22, with approximately $2.26 million sourced from NSW Government and other external grants, including TfNSW funding.
Construction anticipated to commence in early 2027 Clovelly Beach public domain improvements Not started 2. Since 2021/22, Council has spent approximately $2.46 million delivering projects associated with the Clovelly Road precinct and town centre improvements: Project Total Expenditure Clovelly Road Masterplan $73,421 Clovelly Road & Carrington Road Public Plaza $2,322,985 Town Centre Upgrade Program (Clovelly & Burnie St Plaza) $36,411 Federal Road Safety Program (TfNSW) $23,385 Total Expenditure $2,456,202 Funding has been sourced from a combination of: • NSW Government and other external grants, including TfNSW funding (approximately $2.26 million); • Section 7.12 developer contributions (approximately $96,000); • Council infrastructure reserves (approximately $14,000); and • General Council funds (approximately $85,000).
QN14/26 response, expenditure and funding sources
Open original minutes ↗Council officers said they would create a designated website page with updates when available for each adopted master plan, and progress on funded projects would continue to be reported through existing reporting and budgeting processes.
Detailed design is near complete, with construction anticipated to commence in early 2027. 5. All of Council's Masterplans are currently available on Council's public website. Council Officers will create a designated page with updates when available on the website for each adopted Masterplan. Progress on funded projects will continue to be reported through Council's existing reporting and budgeting processes QN15/26 Question with Notice - Question with Notice from Cr Magner - Undergrounding Power Lines - Part B14 and Clovelly Beach (F2014/00358) Questions: 1.
QN14/26 response, website updates and progress reporting
Open original minutes ↗The record contains a note stating that the minutes were confirmed at an Ordinary Meeting on 8 December 2026.
The minutes of this meeting were confirmed at the Ordinary Meeting of Randwick City Council held on Tuesday, 8 December 2026. ................................................... CHAIRPERSON
Confirmation note
Open original minutes ↗Source record
Reporting from the minutes of Randwick City Council’s Ordinary Council meeting held on 17 November 2026, treated here as unconfirmed. The record includes a note stating that confirmation occurred at a meeting on 8 December 2026, after the 19 November 2026 source check; confirmation is therefore not established by this review.
Key facts from the minutes
- Burnie Street Pocket Park has $1,163,589 allocated in the adopted four-year delivery program, with construction anticipated to commence in early 2027.
- Gilderthorpe Avenue and Market Street has $700,000 in grant funding and is expected to follow Burnie Street, but no construction date is recorded.
- Frenchman’s Road streetscape improvements have $140,000 allocated and are described as partially funded.
- Fern Street, Arden Street and Clovelly Beach public-domain improvements are listed as unfunded.
- Council recorded approximately $2.456 million in related precinct and town-centre expenditure since 2021-22.
Why it matters
- Burnie Street has identified funding and an anticipated construction period, but most unfinished projects in the Clovelly Road plan still depend on future budgets or grants.