Orange authorises carpark contractor talks after bids exceed budget

Council rejected every tender for carparks 1A, 1B and 3, ruled out a fresh tender round and authorised negotiations with Zauner Construction and DC Civil Enterprises.

Published 23 November 2026From the 3 November 2026 meeting1 min read
Illustration, not a depiction of the actual site or project.

Reporting from public council minutes. How this article was prepared

Orange City Council has rejected all tenders for carparks 1A, 1B and 3 after they exceeded the available budget, leaving the project’s scope and delivery timeframe unresolved.

At its 3 November meeting, Council decided not to invite fresh tenders, citing the extensive process already undertaken. The chief executive officer was instead authorised to negotiate with the two highest-ranked tenderers, Zauner Construction Pty Ltd and DC Civil Enterprises Pty Ltd.

No contractor was awarded the work under resolution 26/629. Council is to consider a further report recommending the scope of work, timeframe and tender award recommendation if negotiations succeed.

The tender item was considered in closed session under commercial-confidentiality provisions. Its agenda title referred to the Orange Sports Precinct, the Forest Road intersection, carparks 1A, 1B, 3A and 3B and service roads. The operative resolution, however, specifically rejected tenders for carparks 1A, 1B and 3, so the public record does not establish that every component named in the agenda title was rejected.

The resolution was carried without opposition, with Cr J Stedman absent. The public minutes do not disclose the tender prices, how far they exceeded the budget or when the further report will return to Council.

What deserves a closer look

The resolution authorises negotiations rather than awarding the work. The supplied record does not establish that negotiations have begun, and the further report is conditional on successful negotiation.

The agenda lists a broader group of infrastructure works than the operative resolution's specific reference to carparks 1A, 1B and 3. The article therefore does not treat every agenda component as rejected.

Questions for follow-up reporting

What were the tender prices, and by how much did they exceed the available budget?

Will negotiations alter the scope of the carpark works or other Orange Sports Precinct components?

If negotiations succeed, when will Council consider the further report on scope, timeframe and tender award?

What timeframe will be recommended if negotiations succeed?

What happens next

The chief executive officer is authorised to negotiate with Zauner Construction Pty Ltd and DC Civil Enterprises Pty Ltd.

Council is to consider a further report recommending the scope of work, timeframe and tender award, subject to successful negotiation.

Check the record

These passages were matched to the source text. Read them in context in the original minutes.

The minutes identify the tender matter as involving the Orange Sports Precinct, the Forest Road intersection, carparks 1A, 1B, 3A and 3B and service roads, and classify it as confidential on commercial grounds.
6.4 Tender - F4369 - Orange Sports Precinct - Construction of Forest Road intersection, Carparks 1a, 1b, 3a and 3b and Service Roads This item is classified CONFIDENTIAL under the provisions of Section 10A(2) of the Local Government Act 1993, which permits the meeting to be closed to the public for business relating to (c) information that would, if disclosed, confer a commercial advantage on a person with whom the Council is conducting (or proposes to conduct) business.

Item 6.4, closed-meeting classification

Open original minutes ↗
The chief executive officer read out resolutions made in the closed meeting after the ordinary meeting resumed.
The Mayor declared the Ordinary Meeting of Council resumed at 8.57 pm. 7 RESOLUTIONS FROM CLOSED MEETING The Chief Executive Officer read out the following resolutions made in the Closed Meeting of Council.

Section 7, Resolutions from Closed Meeting

Open original minutes ↗
Council rejected all tenders for carparks 1A, 1B and 3 because they exceeded the available budget and decided not to invite fresh tenders because of the extensive process already undertaken.
For: Cr T Mileto (Mayor), Cr K Duffy, Cr T Greenhalgh, Cr G Judge, Cr F Kinghorne, Cr D Mallard, Cr M McDonell, Cr S Peterson, Cr G Power, Cr M Ruddy Against: Nil Absent: Cr J Stedman (Deputy Mayor), Cr J Whitton *Cr Whitton returned to the meeting with the time being 7.36pm* ORDINARY COUNCIL MEETING MINUTES 3 NOVEMBER 2026 Page 12 6.4 TENDER – F4516-1 - ORANGE SPORTS PRECINCT - CONSTRUCTION OF FOREST ROAD INTERSECTION, CARPARKS 1A, 1B, 3A AND 3B AND SERVICE ROADS TRIM REFERENCE: 2026/2125 RESOLVED - 26/629 Cr D Mallard/Cr M McDonell That Council: 1 Rejects all tenders for the Construction of carparks 1a, 1b and 3, Tender Number F4516-1 as a result of all tenders exceeding the available budget. 2 Does not invite fresh tenders due to the extensive process already undertaken for the conduct of this tender. 3 Authorise the Chief Executive Officer to enter into negotiations with the two highest-ranked tenderers, being Zauner Construction Pty Ltd and DC Civil Enterprises Pty Ltd.

Resolution 26/629, paragraphs 1–2

Open original minutes ↗
The voting list records no votes against and Cr J Stedman absent.
4 Consider a further report recommending a scope of work, timeframe and tender award recommendation, subject to successful negotiation. For: Cr T Mileto (Mayor), Cr K Duffy, Cr T Greenhalgh, Cr G Judge, Cr F Kinghorne, Cr D Mallard, Cr M McDonell, Cr S Peterson, Cr G Power, Cr M Ruddy, Cr J Whitton Against: Nil Absent: Cr J Stedman (Deputy Mayor) 6.5 MINUTES OF THE AUDIT, RISK & IMPROVEMENT COMMITTEE - 16 SEPTEMBER 2026 TRIM REFERENCE: 2026/2160 RESOLVED - 26/630 Cr F Kinghorne/Cr S Peterson 1 That Council acknowledge the reports presented to the Audit, Risk & Improvement Committee at its meeting held 16 September 2026.

Resolution 26/629, paragraph 4 and voting list

Open original minutes ↗

Source record

This report is based on Orange City Council’s minutes for its ordinary meeting on 3 November 2026, including resolution 26/629. The supplied record does not establish whether these minutes have been confirmed.

Key facts from the minutes

  • Council rejected all tenders for carparks 1A, 1B and 3 because they exceeded the available budget.
  • Council resolved not to invite fresh tenders.
  • Negotiations were authorised with Zauner Construction Pty Ltd and DC Civil Enterprises Pty Ltd, identified as the two highest-ranked tenderers.
  • A further report is to recommend the scope, timeframe and tender award, subject to successful negotiation.
  • The resolution was recorded as carried with no votes against and Cr J Stedman absent.

Why it matters

  • The project’s cost, scope and timing remain unsettled, with Council authorising negotiations with the two highest-ranked tenderers rather than awarding the work. Any change to the works or timetable may affect contractors and people using parking infrastructure at the Orange Sports Precinct.