City of Wanneroo
Chief Executive Officer Performance Review Committee - 3 Aug 2026 6:00PM
The committee reviewed strong reported Council Plan and capital-project performance, then confidentially recommended that Council consider the CEO’s annual review and possible changes to remuneration and professional development benefits.
Topics
- Wanneroo capital projects finish year $3 million under combined budget
Wanneroo reported $75.1 million in expenditure across its Top Capital Projects portfolio in 2025/26, about $3 million below the combined annual budget, while several major projects advanced.
The result provides residents and contractors with an update on infrastructure delivery, project progress and capital spending. - Wanneroo committee recommends Council consider higher CEO remuneration
The CEO Performance Review Committee recommended Council endorse the 2025/26 annual performance review and consider increasing the CEO’s remuneration and professional development allowance.
The committee’s recommendation could affect senior executive costs, but the extracted minutes do not state that an increase was finally approved. - Capital works performance
Top Capital Projects expenditure totalled $75.1 million against a combined annual budget of $78.1 million, a favourable variance of approximately $3 million.
Residents can track how major capital works spending compared with the annual budget.
Decisions
- CEO annual performance review referred to Council
The committee recommended that Council endorse the report prepared for the Chief Executive Officer’s 2025/26 annual performance review, subject to an absolute majority.
This is a recommendation to Council rather than a final public decision on the review. - Possible increase to CEO remuneration
The committee recommended that Council consider increasing the CEO’s remuneration to the maximum allowed under the State Administrative Tribunal determination for band one local governments.
Any remuneration change would affect the City’s senior executive employment costs; the minutes do not show that the increase was approved. - Possible change to CEO professional development allowance
The committee recommended that Council consider increasing the CEO’s professional development allowance to the same level as council members.
Any change would affect the CEO’s employment benefits; the minutes do not state that the increase was approved.
Discussion
- Council Plan delivery
The Quarter 4 corporate performance update reported that 87 of 94 Council Plan initiatives, or 92.6%, were on target, being monitored or completed.
This indicates the reported level of progress against the Council Plan during the first year. - Capital works performance
Top Capital Projects expenditure totalled $75.1 million against a combined annual budget of $78.1 million, a favourable variance of approximately $3 million.
Residents can track how major capital works spending compared with the annual budget. - CEO annual performance review
The committee’s CEO annual performance review matter was considered confidentially under section 5.23(2)(b) of the Local Government Act 1995 because it related to an individual’s personal affairs.
The public resolution records the committee’s recommendations, while detailed performance-review information remained confidential.
Impacts
- The performance report recorded 92.6% of Council Plan initiatives as on target, being monitored or completed at the end of Quarter 4.
- Major infrastructure projects in Alkimos, Girrawheen and other parts of the City continued to progress.
- Top Capital Projects spending was approximately $3 million below the combined annual budget.
- The committee’s CEO review and proposed benefit changes require consideration by Council; no final remuneration increase is recorded in the extracted material.
Places
- Alkimos Aquatic and Recreation Centre
Major infrastructure project progressed during Quarter 4 - Brazier Road Upgrade
Major infrastructure project progressed during Quarter 4 - Rotary Park Upgrade
Major infrastructure project progressed during Quarter 4 - Girrawheen Hub Redevelopment
Major infrastructure project progressed during Quarter 4 - Civic Centre, 23 Dundebar Road, Wanneroo
Meeting venue and next meeting venue - City of Wanneroo
Council area covered by the performance report
Next
- Council to consider the committee’s recommendations on the CEO’s 2025/26 annual performance review, remuneration and professional development allowance.
Not specified in the extracted minutes - Next Chief Executive Officer Performance Review Committee meeting.
6:00PM, Monday 16 November 2026, Council Chamber, Civic Centre, 23 Dundebar Road, Wanneroo
Extract
Unconfirmed Minutes Chief Executive Officer Performance Review Committee Meeting Minutes 6:00PM, Monday 03 August, 2026 Council Chamber (Level 1), Civic Centre, 23 Dundebar Road, Wanneroo wanneroo.wa.gov.au UNCONFIRMED MINUTES OF CHIEF EXECUTIVE OFFICER PERFORMANCE REVIEW COMMITTEE MEETING HELD ON MONDAY 03 AUGUST, 2026 CONTENTS ITEM 1 ATTENDANCES 1 ITEM 2 APOLOGIES AND LEAVE OF ABSENCE 1 ITEM 3 CONFIRMATION OF MINUTES 1 3.1 MINUTES OF CHIEF EXECUTIVE OFFICER PERFORMANCE REVIEW COMMITTEE MEETING HELD ON 4 MAY 2026 1 ITEM 4 REPORTS 2 4.1 2025-26 QUARTER 4 CORPORATE PERFORMANCE REPORT 2 ITEM 5 CONFIDENTIAL 21 5.1 CHIEF EXECUTIVE OFFICER ANNUAL PERFORMANCE REVIEW 2025/2026 21 ITEM 6 TO BE TABL...