Cycleways and Bicycle Facilities Advisory Committee - 4 Nov 2026

Council’s cycling advisory committee reviewed progress on several walking and cycling projects, including detailed-design milestones, funding opportunities, approval processes and bicycle-parking expansion.

4 November 2026Cycleways and Bicycle Facilities Advisory CommitteeSummary available

Topics

  • Kingsford to Centennial Park cycleway moves into detailed design
    A strongly supported major cycling project is entering detailed design and is positioned to seek construction funding.
    The milestone brings a significant walking and cycling connection closer to delivery, although construction funding and timing are not yet confirmed.
  • Anzac Parade path design to weigh trees, biodiversity and cycling needs
    The Anzac Parade Paths Project is moving into detailed design, with tree retention, biodiversity and user experience identified as key issues.
    The design stage may affect streetscape, environmental outcomes and future cycling conditions, with stakeholder input still available.
  • Lenthall Street cycling link remains on hold as Todman Avenue advances
    One component of a walking and cycling project is progressing while the Lenthall Street section remains deferred.
    Residents receive a clear update on which part of the proposed connection is advancing and which part has no current delivery progress.

Decisions

  • Kingsford to Centennial Park project moves to detailed design
    Council has endorsed progression of the Kingsford to Centennial Park Walking and Cycling Improvements Project to detailed design. Community consultation showed strong support, and consultant programs are being finalised.
    The project is moving closer to construction-funding opportunities and eventual delivery of a major cycling connection.
  • Anzac Parade Paths Project moves to detailed design
    Council has endorsed progression to detailed design. Design work will consider tree retention, biodiversity, path alignment and user experience, with BIKEast to have opportunities to provide input.
    Future path arrangements and impacts on trees, biodiversity and cycling conditions will be shaped during detailed design.
  • Todman Avenue component progresses; Lenthall Street remains on hold
    The Todman Avenue component of the Todman Avenue and Lenthall Street Walking and Cycling Improvements Project is progressing to detailed design. The Lenthall Street component remains on hold.
    Residents may see progress on the Todman Avenue section, while delivery of the Lenthall Street section is deferred.
  • South Coogee to Kingsford project continues through approvals
    The project is progressing through Sydney Water approval processes following a resubmission of drawings. Funding remains secured, with construction anticipated after approvals and tender processes are completed.
    The project has secured funding but construction timing depends on approvals and tendering.
  • Bicycle-parking expansion continues
    Council is installing dedicated parking areas for shared bicycles around major destinations and beaches, with further locations planned across the Randwick local government area and near public transport hubs.
    Residents and shared-bicycle users should see more designated parking, intended to improve accessibility and reduce inappropriate parking behaviour.

Discussion

  • Grant funding for cycling projects
    Officers reported no significant update on Get NSW Active Program and Transport for NSW Walking and Cycling Program funding. Council continues to monitor grant programs and intends to pursue opportunities as projects reach detailed design, including connections to Eastgardens and construction-ready projects.
    External funding could affect which cycling projects proceed to construction and when.
  • Separated cycling through Maroubra Junction
    Options for separated cycling facilities through Maroubra Junction were assessed during concept design and will continue to be reviewed where feasible.
    The design review may influence safety and separation for people cycling through Maroubra Junction.
  • Future network connections and consultation
    General business covered an application to the Federal Active Travel Fund, interim solutions for South Ward bicycle connectivity, cycling-route information in community consultation material, greenway opportunities linking Coogee and Kingsford with neighbouring council areas, and cycling and bicycle parking in the Coogee Foreshore Plan of Management.
    These issues may shape future routes, consultation information and foreshore planning.

Impacts

  • Several cycling projects are progressing through detailed design, but construction dates are not confirmed for most projects.
  • The Lenthall Street component remains on hold.
  • The South Coogee to Kingsford project has secured funding but still requires Sydney Water approvals and tender processes before construction.
  • Dedicated shared-bicycle parking is being expanded around destinations, beaches and public transport hubs.
  • Residents and cycling stakeholders may have further opportunities to comment on the Anzac Parade Paths detailed design.

Places

  • Randwick local government area (local government area)
    Area covered by the committee’s cycling responsibilities and planned bicycle-parking expansion.
  • Kingsford (suburb)
    Included in the Kingsford to Centennial Park and South Coogee to Kingsford walking and cycling projects.
  • Centennial Park (park and project area)
    Destination for the Kingsford to Centennial Park Walking and Cycling Improvements Project.
  • Anzac Parade (road and project area)
    Location of the Anzac Parade Paths Project.
  • Maroubra Junction (locality)
    Location where separated cycling facilities were discussed.
  • Todman Avenue (road and project area)
    Component progressing to detailed design.
  • Lenthall Street (road and project area)
    Project component currently on hold.
  • South Coogee (suburb)
    Included in the South Coogee to Kingsford Walking and Cycling Project.

Next

  • Commence detailed design and finalise consultant programs for the Kingsford to Centennial Park project.
    Next project stage; timing not specified.
  • Progress detailed design for the Anzac Parade Paths Project and provide opportunities for BIKEast input.
    During detailed design; timing not specified.
  • Continue detailed design for the Todman Avenue component while the Lenthall Street component remains on hold.
    Ongoing; timing not specified.
  • Continue Sydney Water approvals, tender preparation and construction planning for the South Coogee to Kingsford project.
    Construction anticipated after approvals and tender processes.
  • Monitor grant programs and pursue suitable funding opportunities as projects progress.
    Ongoing.
  • Install additional shared-bicycle parking areas across the local government area and near public transport hubs.
    Ongoing; timing not specified.

Extract

This is of the Minutes of the Cycleways and Bicycle Facilities Advisory Committee meeting held on 4 November 2026 MINUTES OF CYCLEWAYS AND BICYCLE FACILITIES ADVISORY COMMITTEE MEETING HELD ON WEDNESDAY, 4 NOVEMBER 2026 AT 7:30AM Attendees: Councillors Cr Aaron Magner Councillor – North Ward RCC Cr Dexter Gordon Councillor – Central Ward RCC Stakeholders Elliott Jones BIKEast Sally Durham BIKEast Yvonne Poon BIKEast RCC Officers Eva Havenstein Manager Engineering Services RCC Ross Mills Coordinator Sustainable Transport and Open Space RCC Lachlan Wood Senior Sustainable Transport Officer RCC Robbie Allen Senior Sustainable Transport Officer RCC Bronwyn Englaro Senior Sustainability Officer...