MinutesRadar

funding ยท Ipswich City Council

Ipswich approves extra $2.2 million for Riverlink and Bradfield Bridge reconstruction

The added contingency is intended to help complete flood-recovery works within Queensland Reconstruction Authority funding timeframes.

Published 10 May 2026Meeting 30 April 2026

Ipswich City Council has approved an extra $2.2 million contingency for reconstruction works adjacent to Riverlink and Bradfield Bridge, as the project budget is set to exceed its current allowance.

At its 30 April meeting, council noted that contract 5554 for the Riverlink and Bradfield Bridge reconstruction works, valued at $5,651,735, plus an additional provisional sum of $2,015,417.28 and an allocated contingency of $876,417.28, would be exceeded. Councillors then approved the additional contingency funding and delegated contractual action to the chief executive officer to implement the decision.

The minutes state the extra allocation is to cover potential future variations and help ensure the works can be completed within required Queensland Reconstruction Authority funding timeframes.

For residents and businesses, the decision keeps financial backing in place for ongoing flood-recovery works in a key Ipswich area near Riverlink and Bradfield Bridge. The minutes do not set out new traffic arrangements, but identify the project area as a major works zone linked to reconstruction.

The next step is for the project to continue using the approved contingency if required, with contractual actions to be managed under the chief executive officer's delegated authority.

The same meeting also adopted other committee recommendations, including a temporary parking arrangement for Ipswich Trades Hall in the Nicholas Street Precinct Carpark and further planning steps for Amendment Package 1 affecting 81 East Street.

Reference minutes

Source: Ipswich City Council ordinary meeting minutes, 30 April 2026.

Key facts from the minutes

  • Ipswich City Council approved an additional contingency allocation of $2,200,000 for reconstruction works adjacent to Riverlink and Bradfield Bridge.
  • The council minutes say contract 5554, valued at $5,651,735, plus an additional provisional sum of $2,015,417.28 and an allocated contingency of $876,417.28, will be exceeded.
  • Council said the extra contingency is to cover potential future variations.
  • The stated purpose of the added funding is to help ensure completion within Queensland Reconstruction Authority funding timeframes.
  • Council delegated contractual action to the chief executive officer to implement the decision.

Why it matters

  • The funding approval supports completion of flood-recovery works near Riverlink and Bradfield Bridge within state funding deadlines, affecting a prominent transport and commercial area in Ipswich.