Roads & transport · Georges River Council

Four road humps proposed near Belmore and Forest roads, with work targeted by June 2027

A recommendation in Georges River transport forum minutes proposes three flat-top humps in Peakhurst and Lugarno, while a fourth near 78 Belmore Road would depend on community consultation producing no substantial objections.

Published 13 November 2026From the 28 October 2026 meeting1 min read
Illustration, not a depiction of the actual site or project.

Reporting from public council minutes. How this article was prepared

Residents and road users near four sites in Peakhurst and Lugarno could see new traffic-calming works under a recommendation recorded in Georges River’s Local Transport Forum minutes. It proposes flat-top road humps near 28 and 78 Belmore Road and near 875 and 1140 Forest Road. The recommendation covers signage, line marking and pedestrian fencing, but the 78 Belmore Road site is conditional on consultation producing no substantial objections.

The forum’s 28 October 2026 minutes record the road-hump item as a recommendation, not as a final construction approval. They do not record a vote adopting it or a construction start date.

Council’s Manager Assets and Traffic, S Lindsay, said the project was in the capital works program for traffic facilities and was intended to be completed before the end of June 2027. He said stormwater concerns affecting one hump were expected to be resolved before Christmas 2026.

Mr Lindsay estimated construction would take about three to four weeks, weather permitting, and said work would be undertaken site by site, likely in halves to maintain access along the corridor. The minutes do not specify whether the duration applies to each site or the overall project. They do not give a project cost or define how objections would be assessed as substantial.

What deserves a closer look

The source records a recommendation and staff comments about intended timing, but does not record a vote adopting the road-hump recommendation, final council approval or a construction start date.

The source identifies the capital works program for traffic facilities but does not provide a project cost.

The consultation condition applies specifically to the proposed hump near 78 Belmore Road; the source does not define substantial objections.

Questions for follow-up reporting

Has Georges River Council formally adopted the road-hump recommendation?

When would consultation occur for the proposed hump near 78 Belmore Road?

What threshold would be used to assess substantial objections at 78 Belmore Road?

If the proposal proceeds, when would construction start at each site, and what is the estimated project cost?

What happens next

If the proposal proceeds, the recommendation calls for community consultation on the 78 Belmore Road hump, with installation subject to no substantial objections.

If the project proceeds, the stormwater concerns affecting one hump would need to be addressed; staff anticipated resolving them before Christmas 2026.

If approved, the project would proceed towards staff's stated completion target before the end of June 2027; the construction estimate remains weather-dependent.

Check the record

These passages were matched to the source text. Read them in context in the original minutes.

The record identifies the meeting as the Local Transport Forum meeting of 28 October 2026 and lists S Lindsay as Manager Assets and Traffic.
MINUTES Local Transport Forum Wednesday, 28 October 2026 10:00 AM Dragon Room Civic Centre Hurstville Minutes of Georges River Local Transport Forum Meeting - 28 October 2026 Page 1 COMMITTEE MEETING MEMBERS Councillor Mahoney (Chairperson) Mr L Crompton (Representing Member for Kogarah and Rockdale, Chris Minns MP and Steve Kamper MP) Mr V Le (Representing Transport for NSW) Mr S Braunig (U-GO Mobility Bus Company) Mr J Tran (Representing Member for Oatley, Mark Coure MP) Mr G Wong - St George Cabs – Attended Online GEORGES RIVER COUNCIL STAFF Mr B Spelta (Director Assets & Infrastructure) Mr S Lindsay (Manager Assets and Traffic) Mr A Baradhy

Document title and council staff list

Open original minutes ↗
The road-hump recommendation proposes three flat-top humps near 28 Belmore Road, Peakhurst, and 875 and 1140 Forest Road, Lugarno, with signage, line marking and pedestrian fencing. A fourth near 78 Belmore Road, Peakhurst, is proposed subject to no substantial objections during community consultation.
LTF069-26 Belmore Road and Forest Road, Peakhurst & Lugarno - Proposed Road Humps (Report by Traffic Engineer) RECOMMENDATION That: (a) Flat-top road humps, with associated signage, line marking and pedestrian fencing, be installed at three locations: near 28 Belmore Road, Peakhurst, and near 875 and 1140 Forest Road, Lugarno, as shown in the plans in the report (b) Subject to no substantial objections being received during the community consultation, a flat-top road hump, with associated signage, line marking and pedestrian fencing, be installed near 78 Belmore Road, Peakhurst, as shown in the plan in the report Comments: Mr J Tran commented,

LTF069-26 recommendation

Open original minutes ↗
S Lindsay said stormwater concerns affecting one flat-top hump were expected to be resolved before Christmas and that the intended project delivery remained before the end of the financial year.
Point 14 on 26 says Council is currently finalising the design. What's the expected timeline for that? Mr S Lindsay commented, there's only one flat top speed hump that we're just currently working through some stormwater concerns. So that's anticipated to be resolved this side of Christmas. So it shouldn't delay the overall project in terms of the timeline that we already had, which would be to deliver before the end of the financial year.

LTF069-26 design and timing discussion

Open original minutes ↗
S Lindsay said the project was in the capital works program for traffic facilities. He said work would be undertaken site by site, likely in halves to maintain access, and estimated about three to four weeks, weather permitting.
Mr J Tran commented, so is there funding in this financial year already? Mr S Lindsay commented, yes it's in our capital works program for traffic facilities. Mr J Tran commented, so the construction timeline is expected from start to finish, how long? Mr S Lindsay commented, it will be done per site and likely they will be done in halves just so you can maintain access through that corridor. So probably take place in about 3-4 weeks weather pending.

LTF069-26 funding and construction discussion

Open original minutes ↗
S Lindsay said the project was to be completed before the end of June, rather than by Christmas.
Minutes of Georges River Local Transport Forum Meeting - 28 October 2026 Page 4 Mr J Tran commented, so is it expected to be completed by Christmas? Mr S Lindsay commented, no the project is to be completed before the end of June.

LTF069-26 completion timing clarification

Open original minutes ↗

Source record

Reporting from the minutes of the Georges River Council Local Transport Forum meeting held on 28 October 2026.

Key facts from the minutes

  • The recommendation proposes three road humps near 28 Belmore Road, Peakhurst, and near 875 and 1140 Forest Road, Lugarno.
  • A fourth proposed hump near 78 Belmore Road is conditional on no substantial objections during community consultation.
  • Council staff said the project is in the capital works program for traffic facilities and is intended to be completed before the end of June 2027.
  • One hump still had stormwater concerns. Staff estimated construction at about three to four weeks, weather permitting, without specifying whether that duration applied to each site or the overall project.
  • The minutes do not record final council approval, a construction start date or a project cost.

Why it matters

  • The proposal could change traffic conditions and access near four named road sites, but construction approval is not recorded. The proposed 78 Belmore Road hump is conditional on consultation, and staff identified unresolved stormwater concerns affecting one hump.