The Panel considered three development applications, including consent for modifications to a heritage property in Coogee, and imposed or amended development conditions including a potential $39,744.29 levy before construction can begin.
Topics
- Coogee heritage home modification approved with conservation conditions
The Randwick Local Planning Panel approved changes to alterations and additions at the heritage item at 29 Arcadia Street, Coogee.
The decision affects the future appearance and conservation treatment of a heritage property and nearby residents’ amenity. - Coogee Bay Road development backed after submission concerns addressed through conditions
The Panel supported the application for 173–177 Coogee Bay Road after reviewing a written submission and concluding that the concerns had been addressed in consent conditions.
The decision provides a clear local planning outcome and signals how resident concerns were dealt with in the approval process. - Nearly $40,000 development levy due before construction certificate
A development assessed at $3,974,429 attracts a $39,744.29 Council levy before a construction certificate can be issued.
The charge is a significant project cost and will be indexed to the Sydney CPI before payment.
Decisions
- 29 Arcadia Street, Coogee modification approved
The Panel unanimously granted consent under section 4.56 of the Environmental Planning and Assessment Act 1979 for amendments to approved architectural plans, conservation works, heritage requirements and related conditions for alterations and additions to the heritage item at 29 Arcadia Street, Coogee. Consent is subject to deferred commencement conditions.
The approval allows changes to a heritage property, subject to conservation and other conditions. - 173–177 Coogee Bay Road, Coogee application supported
The Panel considered site visits, submissions and Council’s assessment report, and supported the application for the reasons in that report. It stated that concerns raised in a written submission had been addressed through conditions of consent.
The decision affects a development site on Coogee Bay Road and reflects how community concerns were handled through consent conditions. - Development contribution levy condition applied or amended
For a development with an assessed cost of $3,974,429, a $39,744.29 monetary levy is required before a construction certificate is issued. The amount is indexed quarterly using the Sydney Consumer Price Index and must be confirmed with Council before payment.
The levy is a material development cost and must be paid before construction certification.
Discussion
- Development applications
The meeting dealt with applications at 29 Arcadia Street, Coogee; 1 Hayward Street, Kingsford; and 173–177 Coogee Bay Road, Coogee.
Residents near these sites may be affected by building work, heritage changes, traffic, amenity and construction impacts. - Heritage conservation
The approved modification at 29 Arcadia Street includes changes to architectural plans, a Schedule of Conservation Works, heritage conservation requirements and consent conditions.
The decision affects the treatment and future alteration of a heritage item. - Acoustic standards in mixed-use housing
An amended condition requires residential dwellings in mixed-use development to meet specified acoustic criteria while providing natural ventilation to habitable rooms.
The condition is intended to protect residents from noise while preserving natural ventilation. - Electronic determination
The Panel deliberated and voted electronically based on the information available to it.
The meeting’s planning decisions were made without an in-person public meeting format.
Impacts
- A development contribution levy of $39,744.29, subject to CPI indexation, is payable before a construction certificate can be issued for the relevant development.
- Approved or supported development activity will proceed subject to deferred commencement and other consent conditions.
- Residents near the Coogee and Kingsford sites may experience future construction and amenity impacts.
- Acoustic requirements apply to residential dwellings in mixed-use development, including requirements for natural ventilation.
Places
- 29 Arcadia Street, Coogee
Heritage-item alterations and additions; modification application DA/589/2025/A. - 173–177 Coogee Bay Road, Coogee
Development application considered and supported subject to consent conditions. - 1 Hayward Street, Kingsford
Development application DA/857/2026 was considered; the extracted text includes a requirement for plans to be submitted to and approved by Council’s development assessment manager. - 30 Frances Street, Randwick
Council’s Administrative Centre and location where Development Contributions Plans may be inspected.
Next
- Pay the applicable development contribution levy before a construction certificate is issued, using the indexed amount confirmed by Council.
Before construction certificate issuance. - Submit the required revised or approved plans and documentation to Council’s development assessment team where required by the consent conditions.
Before the relevant condition or construction stage; exact timing is not stated in the extract. - Proceed with the approved development subject to deferred commencement and consent conditions.
After the conditions are satisfied.
Extract
This is of the Minutes of the Randwick Local Planning Panel (Electronic) meeting held on 12 November 2026 MINUTES OF RANDWICK LOCAL PLANNING PANEL (ELECTRONIC) MEETING HELD ON THURSDAY, 12 NOVEMBER 2026 Present: Chairperson: Steven Layman Expert Members: Clare Brown & Kim Burrell Community Representatives: Edna Grigoriou Council Officers present: Coordinator Fast Track Mr M Rivera Coordinator Major Assessments Mr F Macri Senior Environmental Planning Officer Mr J Edmonds Senior Heritage Planner Ms L Sipione Personal Assistant to Manager DA Ms A Halcro Declarations of Pecuniary and Non-Pecuniary Interests A) Nil The Panel deliberated and voted on each matter via an electronic meeting. The re...