community infrastructure project · 1 meeting
Henley Community Centre and Eastern Green
Context
- Tracked aliases include Henley Community Centre and Eastern Green.
Mentions
- Four proponents will enter further due diligence for a possible flexible, multi-use facility.
- The project is moving to a more detailed assessment stage, while Council retains the option not to proceed and prefers a flexible, multi-use community facility.
- The next report should provide more information about options, finances, property implications and delivery pathways.
Decisions
Henley Community Centre and Eastern Green
Council endorsed inviting four preferred expression-of-interest proponents to provide further information and attend due-diligence meetings. Assessment will cover financial capacity, feasibility, community access, delivery timeframes, development approvals, capital works, maintenance, leases and risks. Council made clear that no proponent, lease, development outcome or funding commitment has yet been approved.
The project is moving to a more detailed assessment stage, while Council retains the option not to proceed and prefers a flexible, multi-use community facility.
Topics
Henley facility due diligence
Four preferred proponents will be assessed further for a possible multi-use facility at Henley Community Centre and Eastern Green.
The next report should provide more information about options, finances, property implications and delivery pathways.