Roads & transport · City of Wanneroo

Wanneroo traffic program has 30 projects in pipeline through 2035/36

The Policy Review Committee adopted an updated traffic-management policy without changing the scoring system used to rank local-road requests. The City says its roughly $2 million annual program has enough identified work to extend into 2035/36.

Published 9 November 2026From the 2 November 2026, 6:00pm meeting1 min read
Illustration, not a depiction of the actual site or project.

Reporting from draft minutes. Recorded wording may change when confirmed. How this article was prepared

Thirty Wanneroo traffic projects have reached a score of at least 60 and are considered suitable for progression under a local-road program that the City says could continue through 2035/36 on current funding assumptions.

The Policy Review Committee unanimously adopted the revised Local Area Traffic Management Policy on 2 November, according to unconfirmed minutes. The review updates the policy’s template, authorities and accountabilities, dispute resolution provisions, references, terminology and technical guidance, while retaining the assessment methodology, scoring criteria and project-prioritisation framework introduced in 2024.

The Local Area Traffic Management Program is funded at approximately $2 million a year and covers investigation, design and construction for major and minor traffic projects. The minutes say the 30 projects identified in the current pipeline have achieved a Traffic Management Score of 60 or higher.

The supplied report text does not establish individual construction dates or funding commitments, and the project-priority attachment is not reproduced in readable form. The 2035/36 outlook is based on current allocations and delivery assumptions, while eligible projects may also be considered for State and Federal road-safety grants, including the Black Spot Program.

Historically, about one or two projects a year have reached a score of 60 or more and then progressed into the program. For residents seeking changes on local roads, the existing scoring and prioritisation system remains the basis for assessing requests, with the committee’s resolution recorded as carried unanimously, 8-0, in the unconfirmed minutes.

What deserves a closer look

The adoption motion in P128 is followed by its carried result in P129, establishing a recorded decision rather than an unadopted recommendation.

The eight names listed for the motion in P129 match the declared 8-0 result, with no members listed against it.

The 2035/36 statement is conditional on current funding allocations and delivery assumptions; it is not an individual project construction schedule.

Questions for follow-up reporting

Which of the 30 projects has funding committed in the current budget, and which remain subject to future budgets or grant applications?

What locations, scopes and expected delivery dates apply to the 30 projects scoring 60 or higher?

How will the City report when projects move from assessment into design or construction?

Check the record

These passages were matched to the source text. Read them in context in the original minutes.

The supplied record is labelled unconfirmed minutes of the Policy Review Committee meeting held on 2 November 2026.
Unconfirmed Minutes Policy Review Committee Meeting Minutes 6:00PM, Monday 02 November, 2026 Council Chamber (Level 1), Civic Centre, 23 Dundebar Road, Wanneroo wanneroo.wa.gov.au UNCONFIRMED MINUTES OF POLICY REVIEW COMMITTEE MEETING HELD ON MONDAY 02 NOVEMBER, 2026 CONTENTS ITEM 1 ATTENDANCES 1 ITEM 2 APOLOGIES AND LEAVE OF ABSENCE 1 ITEM 3 PUBLIC QUESTIONS 1 ITEM 4 CONFIRMATION OF MINUTES 2 4.1 MINUTES OF POLICY REVIEW COMMITTEE MEETING HELD ON 31 AUGUST 2026 2 ITEM 5 REPORTS 2 MINOR REVIEWS 2 5.1 LOCAL PLANNING POLICY 3.3: FAUNA MANAGEMENT 2 5.2 LOCAL PLANNING POLICY 4.19: MEDIUM DENSITY HOUSING STANDARDS 16 5.3 LOCAL AREA TRAFFIC MANAGEMENT

Document title and meeting date

Open original minutes ↗
The policy review made minor administrative, governance and editorial changes while retaining the existing assessment methodology, scoring criteria and project-prioritisation framework introduced in October 2024.
The current LATMP and Management Procedure were approved by Council at its meeting 8 October 2024, Item No AS02-10/24 refers. This report provides details of minor amendments. Detail The Local Area Traffic Management Policy has been reviewed to ensure it remains aligned with the City's current policy framework, corporate requirements and relevant industry guidance. The review has resulted in minor administrative, governance and editorial amendments, including: • Updates to ensure consistency with the City's current policy template, including the addition of sections relating to 'Authorities and Accountabilities' and 'Dispute Resolution'. • Updates to references, terminology and strategic alignment to reflect current corporate documents and planning frameworks. • Minor amendments to improve clarity, consistency and ease of interpretation. • Updates to technical references where required to ensure continued alignment with current Austroads and Main Roads Western Australia guidance. The revised Policy maintains the existing assessment methodology, scoring criteria and project prioritisation framework introduced through the comprehensive review adopted by Council in October 2024.

Item 5.3, Background and Detail

Open original minutes ↗
The program is currently funded at approximately $2 million per year and covers investigation, design and construction activities. The City identifies 30 projects with a Traffic Management Score of 60 or higher as suitable for progression through the program.
Accordingly, no substantive changes have been made to the Policy during this review. The framework supports the development and delivery of the Local Area Traffic Management Program, which is currently funded at approximately $2m per annum and supports the investigation, design and delivery of both major and minor traffic management projects. The program includes feasibility investigations, detailed design and construction activities, together with the progression of projects already identified through the Local Area Traffic Management assessment process. The City currently has 30 projects that have achieved a Traffic Management Score of 60 or greater and are considered suitable for progression through the Local Area Traffic Management Program, as provided in Attachment 4.

Item 5.3, Comment

Open original minutes ↗
The City says the identified pipeline can support delivery of traffic-management projects through 2035/36 based on current funding allocations and delivery assumptions.
Based on current funding allocations and delivery assumptions, there is a sufficient pipeline of projects currently identified, to support the delivery of Local Area Traffic Management projects through to 2035/36.

Item 5.3, Comment — pipeline outlook

Open original minutes ↗
Historically, approximately one or two projects each year have achieved a Traffic Management Score of 60 or greater and subsequently progressed into the program.
Historically, approximately one to two projects each year have achieved a Traffic Management Score of 60 or greater and subsequently progressed into the Local Area Traffic Management Program.

Item 5.3, Comment — historical project progression

Open original minutes ↗
Eligible projects may attract State and Federal road-safety funding, including through the Black Spot Program. The City says it will pursue grants where projects demonstrate sufficient merit against the relevant funding criteria.
As the City continues to receive requests for investigations, it is anticipated that additional projects will continue to be identified over time. In addition to annual municipal funding, eligible projects may also attract external funding from State and Federal road safety programs, including the Black Spot Program. Where projects demonstrate sufficient merit against the relevant funding criteria, the City will continue to pursue grant funding opportunities to assist in accelerating project delivery and maximising community benefit.

Item 5.3, Comment — external funding

Open original minutes ↗
The minutes record that the committee adopted the revised Local Area Traffic Management Policy by a unanimous vote of 8-0.
in accordance with the City of Wanneroo's Policy Register. Financial Implications Nil Voting Requirements Simple Majority Moved Cr Rowe, Seconded Cr Bedworth That the Policy Review Committee ADOPTS the revised Local Area Traffic Management Policy as shown in Attachment 3. CARRIED UNANIMOUSLY 8/0 For the Motion: Mayor Aitken, Cr Bedworth, Cr Berry, Cr Figg, Cr Seif, Cr Smith, Cr Rowe and Cr Wright Against the Motion: Nil Attachments: 1⇩. Attachment 1 - Local Area Traffic Management Policy- Current 16/83026[v4] 2⇩.

Item 5.3, adoption motion and recorded result

Open original minutes ↗

Source record

Reporting from the supplied City of Wanneroo unconfirmed Policy Review Committee minutes for the meeting held on 2 November 2026.

Key facts from the minutes

  • The unconfirmed minutes record that the Policy Review Committee adopted the revised Local Area Traffic Management Policy on 2 November 2026 by a vote of 8-0.
  • The review made administrative, governance and editorial changes and retained the existing assessment methodology, scoring criteria and prioritisation framework.
  • The Local Area Traffic Management Program is currently funded at approximately $2 million per year.
  • The City identified 30 projects with a Traffic Management Score of 60 or more as suitable for progression.
  • The City says current funding allocations and delivery assumptions support the identified pipeline through to 2035/36; the supplied report text does not establish project-specific construction allocations.

Why it matters

  • Requests for traffic treatments on Wanneroo’s local roads will continue to be assessed under the existing scoring and prioritisation system. The City identifies 30 projects suitable for progression, but the supplied report text does not establish individual construction funding or delivery dates.