Housing & planning · Toowoomba Regional Council
Toowoomba planning scheme clears council vote, but public consultation must wait
The draft scheme and infrastructure plan will first undergo Queensland Government review, with consultation conditional on technical checks, State approval and any required changes.

Reporting from draft minutes. Recorded wording may change when confirmed. How this article was prepared
According to unconfirmed minutes, Toowoomba Regional Council has endorsed a draft planning scheme that, together with its draft infrastructure plan, could provide housing capacity for more than 315,200 residents and support more than 237,100 jobs at ultimate development. The scheme will not yet change development rules or open for public comment.
The resolution recorded as passed at the council’s 17 November meeting sends the draft Toowoomba Regional Planning Scheme towards a first State Interest Review. It also endorses a draft Local Government Infrastructure Plan, which must undergo a First Compliance Check before it is submitted to the Queensland Government.
The council report sets out further steps to refine the planning scheme and finalise a Feasible Alternatives Assessment Report on its proposed natural-hazard provisions, which address risks including bushfire, flooding and landslides. The assessment is intended to examine alternatives and address potential compensation liability for properties affected by those provisions.
The Queensland Government must notify council within 40 business days whether it can proceed to public consultation or needs more information to address State interests. If the review is completed and any conditions are met, the draft scheme would be released for at least 40 business days of consultation.
After submissions are considered, the scheme may be amended and must be sent for a second State review and approval to adopt. Council would then need to make a later decision on whether to adopt it. The unconfirmed minutes therefore record a significant process step, not approval of the final planning rules.
The draft scheme is intended to guide development, housing supply, population growth, infrastructure and environmental outcomes across the region over a 25-year vision. Council’s report describes the housing and employment figures as capacity at ultimate development, rather than a forecast or commitment that those numbers will be reached.
Detailed attachments containing the draft scheme, proposed refinements and infrastructure plan were listed as confidential in the minutes. Council will receive planning-scheme progress reports every six months through its Planning and Development Committee, replacing the previous quarterly reporting arrangement.
What deserves a closer look
The minutes record approval to advance the statutory planning process, not adoption of the new planning scheme or immediate public consultation.
The supplied record does not establish what State conditions may be imposed or whether natural-hazard provisions will be revised before consultation.
The supplied public minutes disclose the process and broad capacity figures, but do not include the detailed proposed planning controls in the attachments listed as confidential.
Questions for follow-up reporting
What conditions or further information will the Queensland Government require during the first State Interest Review?
When will the detailed draft scheme, maps and proposed provisions be released for public consultation?
Which specific natural-hazard overlays or provisions will be assessed in the Feasible Alternatives Assessment Report, and which properties may be affected?
When will council complete the First Compliance Check, refinements and assessment report?
What happens next
Complete the First Compliance Check of the draft Local Government Infrastructure Plan before submission for State review.
Undertake refinements to the draft planning scheme and finalise the Feasible Alternatives Assessment Report.
Submit the draft planning scheme, draft Local Government Infrastructure Plan, assessment report and associated documents to the Minister for State review.
Await Queensland Government advice under the stated 40-business-day notice requirement on whether consultation can proceed or further information is required.
If State approval and compliance with any conditions allow, release the draft planning scheme for at least 40 business days of public consultation.
Provide half-yearly progress updates to the Planning and Development Committee.
Check the record
These passages were matched to the source text. Read them in context in the original minutes.
The document identifies itself as unconfirmed minutes of Toowoomba Regional Council's Ordinary Meeting held on 17 November 2026.
Toowoomba Regional Council Minutes of the Ordinary Meeting of Council held on Tuesday, 17 November 2026 in the Council Chambers, First Floor, City Hall, 541 Ruthven Street, Toowoomba Page 1 of 151 UNCONFIRMED Toowoomba Regional Council Ordinary Meeting of Council 17 November 2026 TABLE OF CONTENTS 1.Opening of Meeting and Acknowledgement of Traditional Owners 2.Reception of Deputations or Delegations by Appointment 3.Attendance including Apologies, Leave of Absence, Granting Leaves of Absence and Declarations of Conflict of Interest 4.Confirmation of Minutes 5.Business Arising out of Minutes of Previous Meetings 6.Presentation of Petitions 7.Business
Document title and status, page 1
Open original minutes ↗The report sought endorsement of the draft planning scheme and draft Local Government Infrastructure Plan for submission to the Queensland Government for State Interest Review and approval to proceed to public consultation.
12.2 REPORT TITLE Draft Toowoomba Regional Planning Scheme - Endorsement for State Interest Review AUTHOR Ed Johnson, General Manager Planning and Development Group PURPOSE OF REPORT That Council endorse the draft Toowoomba Regional Planning Scheme and draft Local Government Infrastructure Plan for submission to the Queensland Government for State Interest Review and approval to proceed to public consultation in accordance with the Planning Act 2016, Planning Regulation 2017 and Minister's Guidelines and Rules 2020 version 3.
Item 12.2, report title and purpose
Open original minutes ↗The motion provided for endorsement and submission of the draft planning scheme for State Interest Review and approval to proceed to public consultation, and endorsement of the Local Government Infrastructure Plan with a First Compliance Check before submission for State Review.
Page 61 of 151 UNCONFIRMED Toowoomba Regional CouncilOrdinary Meeting of Council 17 November 2026 MOTION Moved by Councillor Tim McMahon, seconded by Councillor Trevor Manteufel That Council: 1. Endorse the draft Toowoomba Regional Planning Scheme (CONFIDENTIAL Attachment 1), incorporating refinements identified as attached (CONFIDENTIAL Attachment 2), and submit it to the Minister for State Development, Infrastructure and Planning for State Interest Review and approval to proceed to public consultation. 2. Endorse the Local Government Infrastructure Plan as attached (CONFIDENTIAL Attachment 3) and conduct First Compliance Check prior to submission to the Minister for State Development, Infrastructure and Planning for State Review.
Item 12.2, substantive motion, clauses 1–2
Open original minutes ↗The motion supported preparation and submission of a draft Feasible Alternatives Assessment Report with the State Interest Review request, replaced quarterly planning-scheme progress reports with half-yearly reports to the Planning and Development Committee, and was recorded as carried.
3. Notify the Minister for State Development, Infrastructure and Planning of this decision, provide the required documents, and undertake the necessary actions for the State Interest Review in accordance with the Chief Executive Notice as attached (Attachment 4). 4. Support the preparation of a draft Feasible Alternatives Assessment Report in accordance with Chapter 4 of the Minister's Rules and Guidelines and submit it to the Minister for State Development, Infrastructure and Planning with the notice requesting a State Interest Review. 5. Note the contents of attached CONFIDENTIAL Attachment 5, CONFIDENTIAL Attachment 6 and CONFIDENTIAL Attachment 7. 6. Receive a progress update on the Draft Toowoomba Regional Planning Scheme through a half-yearly report to the Planning and Development Committee, in lieu of the current quarterly reporting arrangement. CARRIED Page 62 of 151 UNCONFIRMED Toowoomba Regional CouncilOrdinary Meeting of Council 17 November 2026 CORPORATE PLAN REFERENCE 2.9Adopt the Toowoomba Region Futures program, providing a roadmap for managing sustainable growth.
Item 12.2, substantive motion, clauses 3–6 and outcome
Open original minutes ↗The report describes the draft planning scheme as a framework for growth, liveability, infrastructure delivery and environmental outcomes with a 25-year vision.
The draft Planning Scheme is both a legislative obligation and a transformative opportunity to shape the region's growth, liveability, infrastructure delivery, and environmental outcomes for a 25-year vision.
Item 12.2, background
Open original minutes ↗The report says implementation of the draft planning scheme and LGIP could provide housing capacity for more than 315,200 residents and support employment for more than 237,100 jobs at ultimate development.
Analysis of the potential outcomes that may be achieved through the implementation of the draft Planning Scheme and LGIP indicates the capacity to provide housing for over 315,200 residents and support employment for over 237,100 jobs for ultimate development.
Item 12.2, capacity analysis
Open original minutes ↗Subject to council resolution, the report lists a First Compliance Check of the draft LGIP, planning-scheme refinements, finalisation of the draft FAAR and submission of the documents for first State Interest Review as next steps.
Subject to resolution of Council, the next steps will be undertaken in accordance with the Chief Executive Notice (Attachment 4) and the Minister's Guidelines and Rules, including: •Undertake the First Compliance Check of the draft LGIP, in accordance with Sections 16.3 and 16.4 of the Minister's Guidelines and Rules 2020. •Undertake refinements made to the draft planning scheme in accordance with CONFIDENTIAL Attachment 2. •Finalise the draft FAAR. •Submit to the Minister for State Development, Infrastructure and Planning for first State Interest Review the draft Planning Scheme, LGIP, FAAR, and associated documentation, including statement of how advice received through the SIRG (CONFIDENTIAL Attachment 7) has been considered in the preparation of the draft.
Item 12.2, next steps before State review
Open original minutes ↗The report says the Queensland Government must give notice within 40 business days advising whether public consultation can proceed or more information is required, and that consultation would run for at least 40 business days following State Interest Review and compliance with any conditions.
The Queensland Government will advise of any conditions that may apply to the draft Planning Scheme, including the timing on when any conditions must be complied with, and confirmation that Council can proceed to public consultation. In accordance with the Chief Executive Notice, the Queensland Government must give a notice to Council within 40 business days advising that it can proceed to public consultation, or if additional information is required to appropriately address State interests. Following the State Interest Review and subject to compliance with any conditions, the draft Planning Scheme will be released on public consultation for a minimum of 40 business days.
Item 12.2, State response and consultation requirements
Open original minutes ↗Source record
Reporting from the public, unconfirmed minutes of Toowoomba Regional Council's Ordinary Meeting held on 17 November 2026.
Key facts from the minutes
- The unconfirmed minutes record a carried resolution on 17 November 2026 endorsing the draft planning scheme for State Interest Review and the draft Local Government Infrastructure Plan for State review following a First Compliance Check.
- The report identifies a First Compliance Check, planning-scheme refinements and finalisation of a Feasible Alternatives Assessment Report as steps before submission.
- The Queensland Government is to advise within 40 business days whether the scheme can proceed to public consultation or requires further information.
- Any public consultation would run for a minimum of 40 business days and would occur only after State review and compliance with any conditions.
- The draft framework is described as having a 25-year vision, with council reporting capacity for more than 315,200 residents and more than 237,100 jobs at ultimate development.
Why it matters
- The draft framework could affect future development, housing, infrastructure and natural-hazard controls across the Toowoomba Region. Its detailed rules remain subject to State review, public submissions and a later council adoption decision.