Rates & spending · Scenic Rim Regional Council
Scenic Rim carry-forwards ranged from $44.56m to $99.43m over three years
The council said the amounts reflected projects crossing financial years, but its August 2026 financial report’s detailed figures were not included in the draft minutes.

Reporting from draft minutes. Recorded wording may change when confirmed. How this article was prepared
Scenic Rim Regional Council’s capital carry-forwards ranged from $44.56 million to $99.43 million over the last three years, according to a response recorded in the council’s draft 23 September 2026 minutes. The amounts represented 51 per cent to 57 per cent of the relevant year’s capital allocation.
The chief executive officer said carry-forwards kept funding available for approved projects that extended beyond a single financial year. The response listed weather events, contractor availability, supply-chain constraints, grant timelines, land acquisition, design and approval processes, and changes in project scope as possible reasons for projects spanning financial years.
The response said a carry-forward did not represent lost funds or additional expenditure. Instead, it described the remaining budget as being transferred to the following year to complete approved works.
The figures were provided after a public question sought a 10-year, year-by-year breakdown. The draft minutes say the carry-forward amounts are reported in annual financial statements, but do not provide that full breakdown.
At the same meeting, councillors received the unaudited monthly financial report for August 2026. The draft minutes record that an attached report existed, but do not reproduce its detailed financial tables, so the August figures cannot be assessed from the minutes alone. Councillors also noted an update on the 2025-2026 Infrastructure Capital Works Program for June 2026.
What deserves a closer look
The record gives a three-year range rather than the 10-year, year-by-year breakdown requested in the public questions.
The draft minutes identify the August report as an attachment, but the supplied minutes text contains no detailed August financial figures.
The record does not identify which projects account for the reported carry-forward range.
Questions for follow-up reporting
What was the carry-forward amount and percentage for each of the 10 financial years requested by the public questions?
Which projects made up the reported $44.56 million to $99.43 million range, and what were their delivery timeframes?
What were the August 2026 revenue, expenditure, budget and cash figures in the attached unaudited report?
What happens next
The draft 23 September 2026 minutes are marked for confirmation on 28 October 2026.
Check the record
These passages were matched to the source text. Read them in context in the original minutes.
The chief executive said carry-forwards kept funding available to complete approved projects extending beyond one financial year, with possible delivery factors including weather, contractor availability, supply chains, grant timelines, land acquisition, design and approvals, and scope changes.
Ordinary Meeting Minutes 23 September 2026 Page 5 5 Public Question Time 5.1 Questions from Nigel Waistell re Capital Revenue and Expenditure Questions from Mr Waistell dated 31 August 2026: Question 1: "In the last 10 Financial years, how many times has capital revenue been carried forward to next FY due to an underspend?" The Chief Executive Officer provided the following response: "Carry forwards are a common practice across local government and are used to ensure funding remains available to complete approved projects that extend beyond a single financial year. Projects may span multiple years due to factors such as weather events, contractor availability, supply chain constraints, grant funding timelines, land acquisition requirements, design and approval processes, or even changes in project scope.
Item 5.1, public question 1
Open original minutes ↗The public questions asked how often capital revenue had been carried forward in the last 10 financial years and sought amounts and percentages for each year in which a carry-forward occurred.
Ordinary Meeting Minutes 23 September 2026 Page 5 5 Public Question Time 5.1 Questions from Nigel Waistell re Capital Revenue and Expenditure Questions from Mr Waistell dated 31 August 2026: Question 1: "In the last 10 Financial years, how many times has capital revenue been carried forward to next FY due to an underspend?" The Chief Executive Officer provided the following response: "Carry forwards are a common practice across local government and are used to ensure funding remains available to complete approved projects that extend beyond a single financial year. Projects may span multiple years due to factors such as weather events, contractor availability, supply chain constraints, grant funding timelines, land acquisition requirements, design and approval processes, or even changes in project scope. Council reviews its capital program annually and any proposed carry forwards are reported through the budget and financial reporting processes in accordance with legislative and accounting requirements." Question 2: "In each of those years when a carry forward has occurred, what is the amount for each financial year in dollar terms and as a percentage of that year's capital allocation?" The Chief Executive Officer provided the following response: "Large and complex infrastructure projects frequently extend across multiple financial years.
Item 5.1, public questions 1 and 2
Open original minutes ↗Carry-forwards for the last three years were reported as ranging from $44.56 million to $99.43 million, or 51% to 57% of the specific year's capital allocation, with carry-forward amounts provided in annual financial statements.
The carry forward amounts are provided in the annual financial statements. For the last three years, the carry forwards have been between $44.56million to $99.43million or 51% to 57% of the specific year's capital allocation." Ordinary Meeting Minutes 23 September 2026 Page 6 6 Declarations of Prescribed or Declarable Conflict of Interest by Members 6.1 Declaration - Cr Duncan McInnes re Item 11.9 Proposed Issue of Management Agreement to Community Organisation - Harrisville School of Arts Cr Duncan McInnes: I'd like to declare a conflict in Item 11.9 regarding the Harrisville School of Arts which I am a ...
Item 5.1, response to public question 2
Open original minutes ↗A carry-forward was described as remaining budget transferred to the following financial year to complete already approved works, rather than lost funds or additional expenditure.
It is important to note that a carry forward does not represent funds being lost or additional expenditure being incurred. Rather, it reflects the timing of project delivery, with the remaining budget transferred to the following financial year to enable completion of works already approved by Council.
Item 5.1, response to public question 2
Open original minutes ↗Council received the unaudited monthly financial report for August 2026, and the motion carried unanimously.
Moved: Cr Amanda Hay Seconded: Cr Duncan McInnes Motion That Council receive the Unaudited Monthly Financial Report for August 2026. Carried unanimously Ordinary Meeting Minutes 23 September 2026 Page 27 11.14 LATE ITEM - Appointment of Acting Chief Executive Officer Executive Officer: Chief Executive Officer Attachments: Nil Recommendation That, pursuant to section 195 of the Local Government Act 2009, Council appoint the Director Infrastructure Services, James Ruprai, to act as Chief Executive Officer during the period 25 September to 5 October 2026 inclusive.
Item 11.13, motion and outcome
Open original minutes ↗The unaudited monthly financial report for August 2026 is listed as an attachment.
LATE ITEM - Unaudited Monthly Financial Report for August 2026 Executive Officer: Director Corporate and Community Services Attachments: 1. Unaudited Monthly Financial Report August 2026 Recommendation That Council receive the Unaudited Monthly Financial Report for August 2026.
Item 11.13, attachments
Open original minutes ↗Council unanimously carried a motion to note the 2025-2026 Infrastructure Capital Works Program update for June 2026.
Carried unanimously Ordinary Meeting Minutes 23 September 2026 Page 20 11.11 2025-2026 Infrastructure Capital Works Program Delivery - June 2026 Executive Officer: Director Infrastructure Services Attachments: 1. Capital Expenditure Report - June 2026 Recommendation That Council note the Infrastructure Capital Works Program update, as presented. Moved: Cr Duncan McInnes Seconded: Cr Marshall Chalk Motion That Council note the Infrastructure Capital Works Program update, as presented. Carried unanimously Ordinary Meeting Minutes 23 September 2026 Page 21 Corporate and Community Services 11.12 2026-2027 Scenic Rim Community Grants Program Round One, Major and Minor Grants Executive Officer: Director Corporate and Community Services Attachments: Nil Recommendation That Council approve the allocation of funding under Round One of the Scenic Rim Community Grants Program 2026-2027 as detailed in the table below, comprising: (a) Major Community Grants - $168,944.50 across 10 projects;
Item 11.11, heading, motion and outcome
Open original minutes ↗The minutes are marked for confirmation on 28 October 2026.
To be confirmed on 28 October 2026. Cr Tom Sharp Mayor
Minutes confirmation notation
Open original minutes ↗Source record
Scenic Rim Regional Council, draft Ordinary Meeting minutes, 23 September 2026, marked for confirmation on 28 October 2026. This article reports information from the council’s public draft minutes; no events were independently verified.
Key facts from the minutes
- The draft minutes record that Council received the unaudited monthly financial report for August 2026, and the motion carried unanimously.
- Capital carry-forwards over the last three years were reported as ranging from $44.56 million to $99.43 million.
- Those carry-forwards represented 51 per cent to 57 per cent of the relevant annual capital allocation.
- The chief executive said carry-forwards reflected project-delivery timing and were transferred to enable completion of approved works.
- The draft minutes do not include the detailed financial tables from the August report or the requested 10-year annual breakdown.
Why it matters
- The reported range shows that substantial portions of some annual capital allocations were carried into later financial years, but the draft minutes do not identify the projects involved or provide the detailed August financial position.