Works & infrastructure · Scenic Rim Regional Council
Scenic Rim carry-forwards ranged from $44.56m to $99.43m, draft minutes show
Council recorded carry-forwards ranging from $44.56m to $99.43m, equal to 51% to 57% of the relevant annual capital allocation, while noting its June infrastructure update.

Reporting from draft minutes. Recorded wording may change when confirmed. How this article was prepared
Scenic Rim Regional Council’s capital carry-forwards ranged from $44.56 million to $99.43 million in the last three years, according to a response recorded in draft minutes of its 23 September 2026 meeting, with the amounts representing between 51% and 57% of the relevant annual capital allocation.
The response from the chief executive officer said carry-forwards were used to keep funding available for approved projects that extended beyond a single financial year. It said the remaining budget was transferred to the following year to complete approved works, rather than representing lost funds or additional expenditure.
Weather events, contractor availability, supply-chain constraints, grant-funding timelines, land acquisition, design and approval processes, and changes in project scope were listed as factors that could affect delivery timing. The response also said large and complex infrastructure projects frequently extended across multiple financial years.
Separately, council unanimously noted its June 2026 update on the 2025-2026 Infrastructure Capital Works Program. The recorded resolution did not approve new works. The draft minutes give no project-by-project breakdown of the carry-forwards, revised completion dates, contractors or suppliers, leaving the aggregate figures unable to show which projects accounted for the transfers or whether any particular project had been delayed.
What deserves a closer look
The draft minutes present aggregate carry-forward figures and explanations for timing, but do not connect those figures to named projects in the recorded Infrastructure Capital Works resolution.
The infrastructure resolution records a note of the update rather than approval of new works.
Questions for follow-up reporting
Which projects made up the carry-forwards in each of the last three years?
What completion dates apply to projects whose budgets were transferred to a later financial year?
How much of the reported carry-forward range related to externally funded projects?
Did any of the factors listed in the CEO's response affect specific projects in the June 2026 program?
Check the record
These passages were matched to the source text. Read them in context in the original minutes.
The Chief Executive Officer said carry-forwards kept funding available to complete approved projects extending beyond a single financial year.
Ordinary Meeting Minutes 23 September 2026 Page 5 5 Public Question Time 5.1 Questions from Nigel Waistell re Capital Revenue and Expenditure Questions from Mr Waistell dated 31 August 2026: Question 1: "In the last 10 Financial years, how many times has capital revenue been carried forward to next FY due to an underspend?" The Chief Executive Officer provided the following response: "Carry forwards are a common practice across local government and are used to ensure funding remains available to complete approved projects that extend beyond a single financial year.
Item 5.1, response to Question 1
Open original minutes ↗The response said a carry-forward reflected the transfer of remaining budget to the following financial year to complete already approved works, rather than lost funds or additional expenditure.
It is important to note that a carry forward does not represent funds being lost or additional expenditure being incurred. Rather, it reflects the timing of project delivery, with the remaining budget transferred to the following financial year to enable completion of works already approved by Council.
Item 5.1, response to Question 2
Open original minutes ↗The response recorded carry-forwards ranging from $44.56 million to $99.43 million in the last three years, representing 51% to 57% of the relevant year's capital allocation.
The carry forward amounts are provided in the annual financial statements. For the last three years, the carry forwards have been between $44.56million to $99.43million or 51% to 57% of the specific year's capital allocation." Ordinary Meeting Minutes 23 September 2026 Page 6 6 Declarations of Prescribed or Declarable Conflict of Interest by Members 6.1 Declaration - Cr Duncan McInnes re Item 11.9 Proposed Issue of Management Agreement to Community Organisation - Harrisville School of Arts Cr Duncan McInnes: I'd like to declare a conflict in Item 11.9 regarding the Harrisville School of Arts which I am a ...
Item 5.1, response to Question 2
Open original minutes ↗The response listed weather events, contractor availability, supply-chain constraints, grant-funding timelines, land acquisition requirements, design and approval processes, and changes in project scope as possible reasons projects could span multiple years.
Projects may span multiple years due to factors such as weather events, contractor availability, supply chain constraints, grant funding timelines, land acquisition requirements, design and approval processes, or even changes in project scope.
Item 5.1, response to Question 1
Open original minutes ↗The Chief Executive Officer said large and complex infrastructure projects frequently extended across multiple financial years.
Council reviews its capital program annually and any proposed carry forwards are reported through the budget and financial reporting processes in accordance with legislative and accounting requirements." Question 2: "In each of those years when a carry forward has occurred, what is the amount for each financial year in dollar terms and as a percentage of that year's capital allocation?" The Chief Executive Officer provided the following response: "Large and complex infrastructure projects frequently extend across multiple financial years.
Item 5.1, response to Question 2
Open original minutes ↗Item 11.11 concerned the 2025-2026 Infrastructure Capital Works Program Delivery update for June 2026.
Carried unanimously Ordinary Meeting Minutes 23 September 2026 Page 20 11.11 2025-2026 Infrastructure Capital Works Program Delivery - June 2026 Executive Officer: Director Infrastructure Services Attachments: 1.
Item 11.11, item heading
Open original minutes ↗Council unanimously carried a motion to note the Infrastructure Capital Works Program update, as presented.
Capital Expenditure Report - June 2026 Recommendation That Council note the Infrastructure Capital Works Program update, as presented. Moved: Cr Duncan McInnes Seconded: Cr Marshall Chalk Motion That Council note the Infrastructure Capital Works Program update, as presented. Carried unanimously Ordinary Meeting Minutes 23 September 2026 Page 21 Corporate and Community Services 11.12 2026-2027 Scenic Rim Community Grants Program Round One, Major and Minor Grants Executive Officer: Director Corporate and Community Services Attachments: Nil Recommendation That Council approve the allocation of funding under Round One of the Scenic Rim Community Grants Program 2026-2027 as detailed in the table below, comprising: (a) Major Community Grants - $168,944.50 across 10 projects;
Item 11.11, motion and voting outcome
Open original minutes ↗The minutes state they are to be confirmed on 28 October 2026.
To be confirmed on 28 October 2026. Cr Tom Sharp Mayor
Closing confirmation notation
Open original minutes ↗Source record
Reporting from the draft minutes of Scenic Rim Regional Council's Ordinary Meeting held on 23 September 2026. The minutes state they are to be confirmed on 28 October 2026.
Key facts from the minutes
- Council unanimously noted the June 2026 update on the 2025-2026 Infrastructure Capital Works Program.
- Capital carry-forwards in the last three years were recorded as ranging from $44.56 million to $99.43 million, not as a combined three-year total.
- Those carry-forwards represented 51 per cent to 57 per cent of the relevant year's capital allocation.
- The chief executive officer cited weather, contractor availability, supply chains, grant timelines, land acquisition, approvals and scope changes as factors that could affect timing.
- The recorded resolution was to note the update, not to approve a new capital works program.
Why it matters
- The figures show the scale of capital funding carried between financial years, but the draft minutes do not identify the projects behind the transfers or establish when those works will be completed.