road and residential area · 2 meetings
Young Street, Annandale
Mentions
- Residents experience regular above-floor and overland flooding; the proposed drainage works would be assessed here.
- Stormwater infrastructure concerns and flood-risk review.
- Young Street residents experience regular above-floor and overland flooding and have requested installation of a stormwater drainage pipeline.
- The study will determine whether proposed works are technically feasible and safe before any construction or funding application proceeds.
- Construction is not approved at this stage; delivery depends on technical investigations, reprioritisation and future grant funding.
- Could lead to local safety, access and drainage improvements in affected neighbourhoods.
Decisions
Young Street flood mitigation investigation supported
The committee unanimously supported investigating whether the Young Street component of Whites Creek Flood Mitigation Option 2 can be delivered independently, including modelling potential impacts on downstream properties.
Young Street residents experience regular above-floor and overland flooding and have requested installation of a stormwater drainage pipeline.
Whites Creek Upgrade Feasibility Study to proceed
The feasibility study will examine stormwater infrastructure and flood-relief opportunities across the Whites Creek catchment, including the Young Street works, during 2027.
The study will determine whether proposed works are technically feasible and safe before any construction or funding application proceeds.
Future grant funding to depend on study outcomes
If the Young Street works can proceed without detrimental downstream impacts, Council may seek State Government funding to take the project to design stage and pursue funding in 2028. The project priority will also be reassessed through Council's flood mitigation harmonisation study.
Construction is not approved at this stage; delivery depends on technical investigations, reprioritisation and future grant funding.
Marrickville, transport and park-related investigations progressed
Council supported reviews or reports for pedestrian safety at Smidmore Street, parking in Trafalgar Lane, stormwater works in Young Street, and access improvements at Johnson Park.
Could lead to local safety, access and drainage improvements in affected neighbourhoods.
Topics
Young Street flooding
Residents reported regular flooding in Young Street, Annandale, including above-floor and overland flooding during heavy rainfall. The flooding predates the WestConnex tunnel, according to the meeting discussion.
The issue directly affects homes and may lead to future drainage infrastructure if investigations support it.
Whites Creek Flood Mitigation Option 2
The option is identified in the Leichhardt Floodplain Risk Management Plan, ranked 22nd and estimated at $5.7 million. Council is examining whether the Young Street component could be separated at an estimated cost of about $1 million.
Separating the component could provide a more targeted pathway for addressing Young Street flooding, but the cost and priority remain under review.
Property and infrastructure acquisitions
Council authorised steps to acquire Ausgrid land at 30 Brighton Street, Petersham and reviewed confidentiality arrangements after acquisition.
May affect local utility land use and future infrastructure planning.