- Town to receive treated water with fluoride under the resolution
- Water treatment plant and treated water supply project area.
- The decision progresses construction and delivery of the treatment plant, although the tenderer and contract value were not released publicly.
- The treatment plant will be designed to support fluoridation of water supplied to four named towns.
- The resolution creates a future water-treatment change for Cambooya, Greenmount, Nobby and Clifton.
- The project may affect water infrastructure and service delivery in the four-town supply area, but cost and contractor details were not disclosed.
Decisions
Greenmount Water Treatment Plant contract award
Council resolved to award WT32-24/25 Four Communities Project Greenmount Water Treatment Plant to the preferred tenderer identified in the confidential report and authorised the Chief Executive Officer to execute the formal contracts.
The decision progresses construction and delivery of the treatment plant, although the tenderer and contract value were not released publicly.
Fluoride dosing plant added to project
Council resolved to include a fluoride dosing plant in the Greenmount Water Treatment Plant design and construction scope.
The treatment plant will be designed to support fluoridation of water supplied to four named towns.
Fluoridation approved for four-town water supply
Council resolved to add fluoride to treated water produced at the Greenmount Water Treatment Plant and formally advise Queensland Health, with the decision to be published in accordance with the Water Fluoridation Act 2008.
The resolution creates a future water-treatment change for Cambooya, Greenmount, Nobby and Clifton.
Topics
Greenmount Water Treatment Plant contract
The Greenmount Water Treatment Plant contract award was considered in a confidential session because it involved commercial negotiations. The preferred tenderer was not identified in the public minutes.
The project may affect water infrastructure and service delivery in the four-town supply area, but cost and contractor details were not disclosed.
Fluoridation of treated water
The resolution adds design and construction of a fluoride dosing plant to the project and approves fluoridation of treated water produced at the plant.
Residents of Cambooya, Greenmount, Nobby and Clifton are the communities specifically identified as receiving the treated water.
Water infrastructure project updates
Progress was reported on the Perseverance Raw Water Main Renewal, Greenmount Water Treatment Plant, and the Greenmount to Cambooya treated water supply works, including tendering and construction milestones.
Affects water security and delivery of treated water infrastructure in affected communities.