Developer payments push Toowoomba capital spending above October budget Council’s financial report shows $62.71 million in capital expenditure against a $47.06 million year-to-date budget, while its underlying capital works program was running $2.85 million behind plan. Council: Toowoomba Regional Council Meeting: 17/11/2026 9:00 AM Recorded status: noted BRIEF Toowoomba Regional Council’s October financial report records $62.71 million in total capital expenditure against a $47.06 million year-to-date budget, with developer payments identified as a major factor in the $15.65 million variance. The council’s capital works program itself was $2.85 million below budget because of contractor-engagement delays. Operating income was $9.95 million above budget, while unrestricted cash stood at $336.88 million and debt at $176.59 million. KEY FACTS - Council received the financial performance statement for the period ending 31 October 2026, and the motion was carried. - Operating income was $9.95 million above year-to-date budget and operating expenditure was $5.05 million below budget. - Total capital expenditure was $15.65 million, or 33 per cent, above the year-to-date budget, with developer payments a major factor; the capital works program itself was $2.85 million below budget due to slight contractor-engagement delays. - Unrestricted cash was $336.88 million and debt was $176.59 million at 31 October 2026. - The cumulative asset sustainability ratio was 17.62 per cent against a target of more than 60 per cent. ANALYSIS OF THE RECORD - The headline capital variance needs to be read alongside the report's breakdown: developer payments contributed to the overall result, while the capital works program itself was below its year-to-date budget. - The report links the cash level partly to lower-than-forecast capital expenditure, so the cash figure does not by itself demonstrate that the capital delivery program is on schedule. - The asset sustainability result reflects the timing and composition of spending to date and does not establish permanent project delays or asset-maintenance failure. QUESTIONS FOR FOLLOW-UP REPORTING - Which projects account for the reported contractor-engagement delays, and have their delivery dates changed? - How do the $18.9 million in developer payments affect the full-year capital forecast? - When is the remaining renewal spending scheduled during 2026/27? RECORDED NEXT STEPS - Financial performance statements are required to be presented to Council at least monthly. - The report says the overall capital works program is expected to be delivered by 30 June 2027. SOURCE PASSAGES Council received the monthly financial performance statement for the period ending 31 October 2026 and the motion was carried. "RECOMMENDATION That the Monthly Financial Performance Statement for the period ending 31 October 2026 be received. REASONS FOR RECOMMENDATION Nil. Page 19 of 151 UNCONFIRMED Toowoomba Regional CouncilOrdinary Meeting of Council 17 November 2026 MOTION Moved by Councillor Tim McMahon, seconded by Councillor Edwina Farquhar That the Monthly Financial Performance Statement for the period ending 31 October 2026 be received. CARRIED Page 20 of 151 UNCONFIRMED Toowoomba Regional CouncilOrdinary Meeting of Council 17 November 2026 CORPORATE PLAN REFERENCE 4.2Continue to pursue prudent financial management and sustainability." (Item No. 9, motion and outcome) The detailed statement records total capital expenditure of $62.709 million against a year-to-date budget of $47.064 million, approximately $15.65 million or 33 per cent above budget. Developer payments were $18.924 million against a zero year-to-date budget. Capital works program expenditure was $32.143 million against a $34.990 million year-to-date budget, a difference of approximately $2.85 million. "Income Interest ReceivedGrants, Subsidies, Contributions and Donations Operating Income YTD Original Adopted BudgetYTD Actuals Original Adopted Budget 0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000 Labour Operational CostsMaterials, Services and Other Expenditure Expensed Capital - (Prior Year) Finance CostsDepreciation Operating Expenditure YTD Original Adopted BudgetYTD Actuals Original Adopted Budget Page 26 of 151 UNCONFIRMED Consolidated Financial Performance Statement as at 31 October 2026 Original Adopted Budget YTD Original Adopted Budget YTD Variance to Budget YTD % Variance YTD 2025/26 Actuals Notes $'000$'000$'000$'000 Income Capital Revenue Grants, Subsidies and Contributions 60,98712,30812,726 5 41836,967 Infrastructure Charges - Cash 15,50014,85014,835 = (15)05,598 Contributed Assets 23,0004,4804,481 6 100 Sale of Assets 6,099760781 5 213219 Total Capital Revenue 105,58632,39832,823 = 425012,784 Expenditure Capital Expenditure Capital Works Program 155,06434,99032,143 6 2,846824,209 7 Developer Payments 0 0 18,924 5 (18,924)(100)3,083 8 Cressbrook Dam Safety Improvement Project 81,40012,07411,641 6 43346,233 Total Capital Expenditure 236,46447,06462,709 5 (15,645)(33)33,525 CFPS Prior Year Column - The 2025/26 Actuals Column with the CFPS that was presented" (Attachment 1, capital statement headings and expenditure rows) The report rounds the capital works program underspend to $3 million, attributes it to slight contractor-engagement delays and says overall delivery was still expected by 30 June. "Subject to rounding. Expenditure 7. Capital Works Program - $3M below budget due to slight delays associated with contractor engagement, noting current expectation is that overall program is to be delivered by 30 June." (Attachment 1, note 7) The report identifies developer payments as $18.9 million above budget. "8. Developer Payments - $18.9M above budget. YTD Actuals $'000 CAPITAL Page 27 of 151 UNCONFIRMED Consolidated Financial Performance Statement as at 31 October 2026 Sustainability MeasuresTarget (Tier 2) 2026/27 Original Budget 2026/27 YTD Actuals Asset Sustainability RatioGreater than 60%63.70%17.62% Asset Consumption RatioGreater than 60%65.95% Notes ## ## ## ## ## ## ## ## The YTD ratio of 65.95% is above target of greater than 60% indicating that over time, Council is sustaining its asset needs." (Attachment 1, note 8) The detailed statement records operating income of $246.51 million and operating expenditure of $148.52 million, rounded to two decimal places. "Att 3 - CONFIDENTIAL - Monthly Investment Report Page 23 of 151 UNCONFIRMED Attachment 1 Consolidated Financial Performance Statements Page 24 of 151 UNCONFIRMED Original Adopted Budget YTD Original Adopted Budget YTD Variance to Budget YTD % Variance YTD 2025/26 Actuals Notes $'000$'000$'000$'000 OPERATING 31 October Recurrent Revenue Rates and Levies407,498 203,381 206,357 = 2,9771188,499 1 Fees, Charges and Other Income 68,37023,96326,272 5 2,3091020,848 2 Interest Received 13,0304,7607,784 5 3,024643,973 3 Grants, Subsidies, Contributions and Donations 8,1534,4546,094 5 1,6403711,610 4 Total Recurrent Revenue 497,051236,558246,507 5 9,9504224,931 Expenditure Recurrent Expenses Labour Operational Costs159,903 48,601 48,486 = 115049,901 Materials, Services and Other Expenditure170,892 51,874 46,608 6 5,2661043,151 5 Expensed Capital - (Prior Year)00156 5 (156)(100)0 6 Finance Costs14,288 4,220 4,372 5 (152)(4)4,603 Depreciation 146,568 48,870 48,896 = (26)048,151 Total Recurrent Expenses 491,650153,565148,518 6 5,0473145,806 NET OPERATING RESULT ATTRIBUTABLE TO COUNCIL5,40182,99397,98914,9971879,125 OPERATING SURPLUS RATIO1.09%35.08%39.90% Operating Expenditure 6." (Attachment 1, recurrent revenue and recurrent expenses totals) The report records operating income $9.95 million above budget, including rates and levies $2.98 million above budget due to increased water consumption; fees and charges $2.31 million above budget due to increased activity and private works; interest $3.02 million above budget; and grants, subsidies, contributions and donations $1.64 million above budget due to additional DRFA revenue from the January 2024 event. "Consolidated Financial Performance Statements (Attachment 1) incorporates the following reports: Consolidated Financial Performance Statements •Operating income - Favourable variance of $9.95M or 4% including: oRates and Levies above budget $2.98M or 1% due to increased water consumption. oFees and Charges above budget $2.31M or 10% due to increased activity and private works. oInterest Received above budget $3.02M or 64% due to additional grant funding received in late June 2026. oGrants, Subsidies, Contributions and Donations above budget $1.64M or 37% due to additional DRFA revenue from January 2024 event, acquittal results exceeding 99% estimated. •Operating expenditure - Favourable variance of $5.05M, including: oMaterials, Services and Other Expenditure below budget by $5.27M or 10% associated with timing at this stage across multiple services." (Item No. 9, operating income commentary) The report records operating expenditure $5.05 million below budget and materials, services and other expenditure $5.27 million below budget, associated with timing across multiple services. "oGrants, Subsidies, Contributions and Donations above budget $1.64M or 37% due to additional DRFA revenue from January 2024 event, acquittal results exceeding 99% estimated. •Operating expenditure - Favourable variance of $5.05M, including: oMaterials, Services and Other Expenditure below budget by $5.27M or 10% associated with timing at this stage across multiple services." (Item No. 9, operating expenditure commentary) The materials, services and other expenditure underspend was associated with timing of contract costs for utilities and services, including computer software, consulting, construction material and electricity. "5. Materials, Services and Other Expenditure - $5.3M below budget associated with timing at this stage with contract costs for utilities and services including computer software, consulting, construction material and electricity." (Attachment 1, note 5) SOURCES https://toowoomba.civicclerk.com.au/web/UserControls/DocPreview.aspx?m=1&aoid=1672&token=77144bca-0ae8-45de-b8cb-182d39d3c4d5 https://minutesradar.com/news/toowoomba-civicclerk-ordinary-meeting-of-council-17-november-2026-17-11-2026-9-00-am-minutes-developer-payments-push-toowoomba-capital-spen-7f3fe50b13/ Prepared from public council minutes using automated drafting and checks. No meeting attendance or interviews are implied. Check the original record and seek comment before republishing claims or analysis. Illustrations are generic, not depictions of actual projects.