Coogee development faces $39,744.29 levy before construction certificate Randwick’s planning panel approved a modification at 173 - 177 Coogee Bay Road, with the contribution subject to Sydney CPI indexation before payment. Council: Randwick City Council Meeting: 12 Nov 2026 Recorded status: approved BRIEF A Randwick planning panel approved a Section 4.55 modification for 173 - 177 Coogee Bay Road, Coogee, with a stated $39,744.29 development contribution payable before a construction certificate. The levy is based on a $3,974,429 development cost and will be indexed to the Sydney CPI. The consent also changes the development’s internal layout, lift arrangements and acoustic requirements. KEY FACTS - The panel approved a Section 4.55 modification for 173 - 177 Coogee Bay Road, Coogee, on 12 November 2026. - The stated levy is $39,744.29, based on a development cost of $3,974,429. - Payment is required before a construction certificate is issued. - The levy is indexed using quarterly changes in the Sydney Consumer Price Index, and the consent directs the applicant to contact Council for the indexed amount before payment. - The amended consent includes acoustic criteria for residential dwellings in the mixed-use development. - The minutes record the resolution as carried unanimously. ANALYSIS OF THE RECORD - The levy amount stated in the consent is not necessarily the amount payable later because the condition provides for CPI indexation. - The minutes establish a payment condition but do not establish a construction certificate date or construction start date. - The acoustic condition combines specified acoustic criteria with a requirement for natural ventilation in all habitable rooms. QUESTIONS FOR FOLLOW-UP REPORTING - When will the applicant seek a construction certificate for the Coogee Bay Road development? - What indexed contribution amount will Council confirm when payment is due? - How will compliance with the amended acoustic requirements be demonstrated for the residential dwellings? RECORDED NEXT STEPS - The applicant must pay the applicable indexed contribution before a construction certificate is issued. - The consent directs the applicant to contact Council for the indexed contribution amount before payment. - The approved modification remains subject to the consent conditions. SOURCE PASSAGES The panel approved a Section 4.55 modification for 173–177 Coogee Bay Road, including changes to bathrooms, units and the lift. "D74/26 Development Application Report - 173-177 Coogee Bay Road, Coogee (DA/535/2024/A) RESOLUTION: That the RLPP, as the consent authority, approve the application made under Section 4.55 of the Environmental Planning and Assessment Act 1979, as amended, to modify Development Application No. DA/535/2024 for Section 4.55(2) Modification to approved development for a new second bathroom to the 2-bedroom units, extension of the 1-bed units within the existing building fabric and re-orientation of the lift to meet fire requirement including amendments to the residential lobby, at No. 173-177 Coogee Bay Road, in the following manner: • Amend Condition 1 to read: The development must be implemented substantially in accordance with the plans and supporting documentation listed below and endorsed with Council's approved stamp: Development must be implemented substantially in accordance with the plans and supporting documentation listed below and endorsed with Council's approved stamp, except where amended by Council in red and/or by other conditions of this consent: Plan Drawn by Dated Received by Council DA02 (Rev." (D74/26 development application report and resolution) The quoted text calls for deleting Condition 18 and amending Condition 6 to state a $39,744.29 levy based on a development cost of $3,974,429. "• Delete Condition 18 • Amend Condition 6 to read: In accordance with Council's Development Contributions Plan effective from 21 April 2015, based on the development cost of $3,974,429 the following applicable monetary levy must be paid to Council: $39,744.29." (Deletion of Condition 18 and amended Condition 6) The levy must be paid by cash, bank cheque or credit card before a construction certificate is issued and is subject to quarterly CPI indexation using the All Groups, Sydney index. The condition directs the applicant to contact Council for the indexed contribution amount before payment. "The levy must be paid in cash, bank cheque or by credit card prior to a construction certificate being issued for the proposed development. The development is subject to an index to reflect quarterly variations in the Consumer Price Index (CPI) from the date of Council's determination to the date of payment. Please contact Council on telephone 9093 6000 or 1300 722 542 for the indexed contribution amount prior to payment. To calculate the indexed levy, the following formula must be used: IDC = ODC x CP2/CP1 Where: IDC = the indexed development cost ODC = the original development cost determined by the Council CP2 = the Consumer Price Index, All Groups, Sydney, as published by the ABS in respect of the quarter ending immediately prior to the date of payment CP1 = the Consumer Price Index, All Groups, Sydney as published by the ABS in respect of the quarter ending immediately prior to the date of imposition of the condition requiring payment of the" (Amended Condition 6: payment and indexation) The wording provided for Condition 23 requires residential dwellings in mixed-use development to satisfy acoustic criteria while providing natural ventilation to all habitable rooms. It specifies repeatable maximum one-hour LAeq levels that should not be exceeded with windows closed: 35 dB(A) in sleeping areas between 10pm and 7am, 40 dB(A) in sleeping areas over 24 hours and 50 dB(A) in living areas over 24 hours. "levy. Council's Development Contributions Plans may be inspected at the Customer Service Centre, Administrative Centre, 30 Frances Street, Randwick or at www.randwick.nsw.gov.au. • Amend Condition 23 to read: MINUTES OF RANDWICK LOCAL PLANNING PANEL MEETING 12 NOVEMBER 2026 This is page 10 of the Minutes of the Randwick Local Planning Panel (Electronic) meeting held on 12 November 2026 Residential dwellings in mixed-use development are to be designed and constructed to satisfy the following acoustic criteria while concurrently providing natural ventilation to all habitable rooms: In naturally ventilated spaces – the repeatable maximum L Aeq (1 hour) should not exceed: • 35 dB(A) between 10.00pm and 7.00am in sleeping areas when windows are closed, • 40 dB(A) in sleeping areas when windows are closed (24 hours), • 50 dB(A) in living areas when windows are closed (24 hours)." (Amended Condition 23) The modification summary records a determination date of 12 November 2026. "Modification Summary Application Number (PAN#) Determination Date Modification Description PAN-670664 12 November 2026 Amend condition 1 for internal and external amendments. Amend condition 6 to update contribution cost." (D74/26 modification summary) The panel said it reviewed the written submission and considered that the concerns raised had been addressed in the consent conditions. "The Panel reviewed the written submission and considers that the concerns raised have been addressed in the conditions of consent. The Panel supports the application for the reasons given in the assessment report." (D74/26 reasons) The minutes record the resolution as carried unanimously. "CARRIED UNANIMOUSLY. The meeting closed at 3:04pm. CONFIRMATION OF MINUTES BY PANEL MEMBERS Steven Layman (Chairperson) Clare Brown Kim Burrell Edna Grigoriou" (D74/26 voting outcome) SOURCES https://randwick.infocouncil.biz/RedirectToDoc.aspx?URL=Open/2026/11/PPE_12112026_MIN_4351_AT.PDF https://minutesradar.com/news/randwick-infocouncil-randwick-local-planning-panel-electronic-12-nov-2026-12-nov-2026-minutes-coogee-development-faces-39-744-29-levy-befor-8b258412a9/ Prepared from public council minutes using automated drafting and checks. No meeting attendance or interviews are implied. Check the original record and seek comment before republishing claims or analysis. Illustrations are generic, not depictions of actual projects.