Liverpool committee notes $243.9m capital program as $17.1m is spent The Governance Committee received and noted the August finance report, which recorded $87.5 million in revenue and below-benchmark capital spending at 31 August. Council: Liverpool City Council Meeting: 13 October 2026 Recorded status: noted BRIEF Liverpool City Council’s Governance Committee received and noted an August finance report recording $87.5 million in year-to-date revenue and $49.8 million in operating expenditure. Revenue was $5.5 million ahead of benchmark and spending $760,000 below it. Of the $243.9 million 2026-27 capital works program, $17.1 million had been spent by 31 August, with delivery to remain under review. KEY FACTS - The report covered council’s financial position at 31 August 2026. - Year-to-date revenue was $87.5 million, $5.5 million ahead of the straight-line benchmark. - Operating expenditure was $49.8 million, $760,000 below benchmark. - The 2026-27 capital works program totals $243.9 million, with $17.1 million spent by 31 August. - The investment portfolio was $516.1 million with an annualised return of 4.87 per cent. - The Governance Committee received and noted the report. ANALYSIS OF THE RECORD - The source describes council's reported financial position and records the committee's receipt and noting of the report. It does not independently verify the August figures. - The report identifies capital delivery and expenditure timing as explanations for below-benchmark spending, but does not identify the affected projects or revised delivery dates. QUESTIONS FOR FOLLOW-UP REPORTING - Which capital projects account for the $17.1 million of spending being below the year-to-date benchmark? - What revised delivery dates, if any, apply to projects affected by the reported timing issues? - Will later finance reports show whether capital spending has returned to its planned profile? RECORDED NEXT STEPS - The report says continued focus will be placed on capital program delivery, key revenue assumptions and emerging financial risks throughout the remainder of the 2026-27 financial year. SOURCE PASSAGES The August report recorded $87.5 million in year-to-date revenue, $5.5 million ahead of the straight-line benchmark, and $49.8 million in operating expenditure, $760,000 below benchmark. It said no material financial sustainability or budget-compliance issues had been identified at that stage of the financial year. "Chairperson BUDGET COMMITTEE ITEM NO: ITEM 07 FILE NO: 323710.2026 SUBJECT: Monthly Finance & Risk Report FY 2026-27 (August 2026) Executive Summary As at 31 August 2026, Council's financial position remains sound, with year-to-date revenue of $87.5 million representing 17.8% of the annual budget and performing $5.5 million ahead of the straight-line benchmark. Operating expenditure of $49.8 million represents 16.4% of the annual budget and remains $760k below benchmark, reflecting prudent expenditure management. No material financial sustainability or budget compliance issues have been identified at this stage of the financial year." (Item 07, Monthly Finance & Risk Report FY 2026-27 (August 2026)) The 2026-27 capital works program totalled $243.9 million, with $17.1 million spent by 31 August 2026, representing 7.0 per cent of the annual budget. The report attributed below-benchmark spending largely to project delivery and expenditure timing. "The 2026-27 capital works program totals $243.9 million, with expenditure of $17.1 million incurred to 31 August 2026, representing 7.0% of the annual budget. While capital expenditure is below the year-to-date benchmark, this largely reflects project delivery and expenditure timing across a number of major programs and will continue to be closely monitored." (Item 07, Monthly Finance & Risk Report FY 2026-27 (August 2026)) The report identified employee costs, grant revenue targets, Financial Assistance Grant timing, rates revenue, investment income and development contributions for ongoing management oversight. "Key areas requiring ongoing management oversight include employee costs, achievement of grant revenue targets, Financial Assistance Grant timing, rates revenue performance, and the continued strength of investment income and development contributions." (Item 07, Monthly Finance & Risk Report FY 2026-27 (August 2026)) The investment portfolio was $516.1 million, had an annualised return of 4.87 per cent and was reported as compliant with the Investment Policy. Its return exceeded the ABBI benchmark by 0.88 percentage points. "Council's investment portfolio of $516.1 million remains fully compliant with the Investment Policy and achieved an annualised return of 4.87%, out-performing the ABBI benchmark by 0.88 percentage points." (Item 07, Monthly Finance & Risk Report FY 2026-27 (August 2026)) Rates and annual-charge collections totalled $58 million, representing 25.3 per cent of collectible revenue. The report said collection performance was tracking in line with expectations for that stage of the financial year. "Rates and annual charges collections totalled $58.0 million, representing 25.3% of collectible revenue, with collection performance tracking in line with expectations for this stage of the financial year." (Item 07, Monthly Finance & Risk Report FY 2026-27 (August 2026)) The report said continued focus would be placed on capital program delivery, key revenue assumptions and emerging financial risks throughout the remainder of the financial year. "Continued focus will be placed on capital program delivery, key revenue assumptions and emerging financial risks throughout the remainder of the financial year. RECOMMENDATION That the Governance Committee receives and notes the Report." (Item 07, concluding assessment) The minutes identify the Governance Committee meeting as held on 13 October 2026 and confirmed on 10 November 2026. "1 Minutes of the Governance Committee Meeting held on Tuesday, 13 October 2026 and confirmed on Tuesday, 10 November 2026 ........................................... Chairperson MINUTES OF THE GOVERNANCE COMMITTEE MEETING HELD ON 13 OCTOBER 2026 PRESENT: Deputy Mayor Harle (Chair) Councillor Adjei Councillor Ammoun Councillor Harte (Online) Councillor Macnaught Mr Peter Scicluna, Acting Chief Executive Officer Mr Farooq Portelli, Director Corporate Services Ms Tina Bono, Director Community & Lifestyle Ms Lina Kakish, Director Planning & Compliance Mr Vishwa Nadan, Chief Financial Officer Ms Clare Mongjaay, Acting Secretariat Ms Natalie Tan, Councillor" (Minutes title and confirmation heading) SOURCES https://liverpool.infocouncil.biz/RedirectToDoc.aspx?URL=Open/2026/10/GOV_20261013_MIN_779.PDF https://minutesradar.com/news/liverpool-infocouncil-governance-committee-meetings-13-oct-2026-13-oct-2026-minutes-liverpool-committee-notes-243-9m-capital-program-as-17-1m-is-spent/ Prepared from public council minutes using automated drafting and checks. No meeting attendance or interviews are implied. Check the original record and seek comment before republishing claims or analysis. Illustrations are generic, not depictions of actual projects.